Amber is not a category, it is a clock. Under the SEMA code, damage classified amber that has not been rectified within four weeks becomes red, requiring immediate offloading. A great many sites treat amber as a standing state and hold amber items on a list for months, at which point the classification on the report no longer describes the racking.

KnowSafeInspectionSAF-131Pinned in navigation58 fields across 7 sectionsFull researchSee the form

Reviewed by Siddarth SinghCSPLast reviewed 16 August 2026

Basis
ISO 45001 cl.8.1
Workspace
KnowSafe
Form type
Inspection
Amber
Escalates to red at 4 weeks
Expert inspection
Annually as a minimum

The short version

  • Amber escalates to red if remedial work has not been carried out within four weeks of the damage first being noted. An inspection report can therefore contain two kinds of red: newly identified serious damage, and amber that was left.
  • Offloading means removing everything supported by the affected component, which for a frame member includes loads on levels above and frequently in adjacent bays.
  • Expert inspection by a competent person is recommended at least annually, more often for high-volume operations, supported by regular internal checks and an immediate check after any impact.
  • Damage patterns are more informative than individual findings. Repeated damage at the same locations points at aisle width, layout or traffic flow rather than at driver behaviour.
  • Load notices must reflect the current configuration. Beam levels moved during a reconfiguration change the permitted load, and the notice is rarely updated with them.
  • The relevant standards are EN 15635 for use and maintenance, SEMA codes of practice, and HSG76 guidance, with PUWER supplying the legal duty.

What this is

What is a racking inspection?

What is a racking inspection?

A structured examination of pallet racking for damage, deflection, missing components, loading and installation faults, classifying each finding by severity and specifying the action and timescale required. Under PUWER, racking is work equipment and must be inspected and maintained safe.

What does the traffic light system mean?

Green means damage within SEMA allowable limits: record and monitor at future inspections. Amber means damage exceeding allowable limits requiring action, with the location offloaded as soon as practicable and not reloaded until rectified. Red means damage beyond allowable limits requiring immediate offloading and isolation.

Scope

When is a racking inspection required?

This covers inspection of installed racking. Design, installation and load calculation are separate activities.

Use this template when

  • Routine internal inspection at defined intervals by a trained person responsible for rack safety
  • Expert inspection by a competent external inspector, annually or more frequently by risk
  • Immediate inspection following any impact, however minor it appears
  • After reconfiguration, beam relocation or a change in stored product or handling equipment
  • Following a near miss involving racking, a load fall or a truck collision

Do not use it for

  • Racking design and load calculation, which is an engineering activity performed by the supplier or a specialist
  • Installation certification, which confirms the racking was erected to specification
  • Truck and driver assessment, which addresses the cause of most impact damage
  • The load notice itself, which is a standing document this inspection verifies
  • Warehouse layout and traffic management assessment, which addresses why damage recurs

Compliance mapping

Which ISO 45001 cl.8.1 requirements does this satisfy?

Racking safety sits under work equipment duties, with a European standard and industry codes supplying the method.

ClauseRequirementWhere it lands
PUWER reg.4Work equipment suitable for its purpose and the conditions of useStructure
PUWER reg.5Work equipment maintained in efficient working order and good repairDamage found
PUWER reg.6Inspection by a competent person at suitable intervals and after exceptional circumstancesHeader
EN 15635Steel static storage systems: application and maintenance of storage equipment, including damage assessmentDamage found
SEMA code of practiceRed, amber and green risk classification with defined actions and the four-week escalation ruleSummary
HSE HSG76Warehousing and storage guidance including racking inspection and damage responseHeader
OSHA 1910.176(b)Storage of material secure against sliding or collapse (US general industry route)Loading
ISO 45001 cl.8.1Operational control including inspection regimes for equipment in useResult

What it does not cover

  • Racking design and load calculation, an engineering activity performed by the supplier or a specialist.
  • Installation certification, confirming erection to specification.
  • The load notice, a standing document this inspection verifies rather than produces.
  • Truck and driver assessment, which addresses the cause of most impact damage.
  • Layout and traffic management assessment, which addresses why damage concentrates where it does.

How to complete it

How to complete a racking inspection, step by step

Classify consistently, act to the timescale the classification carries, and read the pattern rather than the individual finding.

Classify against allowable limits, not by appearance

SEMA sets measurable tolerances for deflection and deformation of beams and uprights. Classification should be made against those figures rather than by judgement about how bad it looks, because a modest visible bend in an upright can exceed the limit while a more obvious mark on a beam does not.

Treat amber as a dated obligation

Record the date the damage was first noted, because that is what starts the four-week clock. Amber items should be offloaded as soon as practicable and not reloaded until rectified, and where four weeks pass without remedial work the classification becomes red. A list of aged amber items is a list of red items with the wrong colour on it.

Offload what the component supports

Offloading a beam means clearing that beam. Offloading a frame member means clearing what it supports, including levels above and, depending on the construction and the damage, adjacent bays. Where there is doubt, clearing adjacent bays and seeking advice is the correct response rather than a cautious one.

Read the damage map

Plot findings by location across inspections. Damage that concentrates at aisle ends, at particular pick faces or on one side of a racking run is telling you about aisle width, turning circles, lighting or traffic flow. That is a layout finding, and it will keep producing damage regardless of how promptly each individual item is repaired.

What auditors find

Most common racking inspection findings

Racking findings concentrate on classification discipline and on the recurrence nobody addressed.

FindingClauseWhat fixes it
Amber items carried across multiple inspections without rectification.SEMA codeAmber becomes red after four weeks; an aged amber list is a red list.
Damage classified by appearance rather than against allowable limits.EN 15635Measure against SEMA tolerances; visible severity and measured deviation differ.
Affected location not offloaded after an amber or red classification.SEMA codeOffload what the component supports, including levels above and adjacent bays where relevant.
No inspection following a known impact.PUWER reg.6Inspect immediately after any impact; exceptional circumstances trigger inspection under PUWER.
Load notices not updated after beam levels were moved.EN 15635Reconfiguration changes permitted loads; the notice must follow the configuration.
Damage recurring at the same locations with no layout review.ISO 45001 cl.8.1Recurrence is a layout or traffic finding, not a repair finding.
Internal inspections performed by someone with no rack safety training.PUWER reg.6Appoint and train a person responsible for rack safety; competence is the requirement.
Missing beam locks or safety pins not treated as significant.EN 15635A dislodged beam is a collapse mechanism; missing locks are not cosmetic.
Repairs made with non-original components.EN 15635Replace like for like; mixed components alter the load path in ways the design did not assume.
Damage reported by operators discouraged by the consequences.ISO 45001 cl.5.4Impacts must be reportable without penalty, or damage is discovered at inspection instead.

Case in point

Case in point: forty amber items and a definition

A distribution centre ran expert racking inspections annually and internal checks monthly. The annual report classified six items red and forty-one amber. The red items were rectified within a week. The amber items were added to a maintenance list and scheduled for attention when a contractor was next on site, which turned out to be four months later.

Under the SEMA code, amber damage not rectified within four weeks of first being noted should be treated as red risk requiring immediate offloading. Three months into that period, the site was operating with forty-one locations that were red by the code it had commissioned the inspection against, all of them loaded.

The inspection report was accurate and the classification was correct on the day it was written. What had not been read was the sentence explaining what amber obliges you to do and by when.

The template

The template, field by field

The form exactly as it installs. Every field, option, score and conditional rule is editable, and the links to other templates come with it.

58fields
7 sections
Reference
SAF-131
Archetype
Inspection
Record ID
INSP-2026-000
Scoring
Pass rate
Direction
High is good
Singleton
Yes
Basis
ISO 45001 cl.8.1
Links
Links Storage location register, Work orders
Tags
Warehouse, Racking
Sections
7
Fields
58
Follow up fields
4
Repeating sections
1
Links out
5
Field typesOwn ID, generated on saveCase thread and parentPick list from a registryLinked to another templateFollow up, dashed outlineScored

Header

15 fields
Text

Inspection ID*

Generated on save

Auto sequence. Format INSP-2026-00000.

The record's own ID. Other templates point at this value.

Single Choice

Status*

Scored

Drives who this goes to next.

  • Planned2 pts
  • In progress2 pts
  • Complete3 pts
  • Deferred0 pts
  • Open0 pts
  • Closed3 pts
  • Overdue0 pts
Date & Time

Date and Time*

Users

Completed By*

Pick List

Site*

From FDN-001 Site NameFilter: Status is Active
Text

Site ID*

Linked

Format SITE-000.

Links to FDN-001 Site ID

Single Choice

Area

Optional

The area within the site.

Cutting roomBoning hallPackingChill storeFreezerPasteurisingFillingCulture roomDespatchYardWorkshopPlant roomOffices
Location

Exact Location

Optional

Drop a pin for anything hard to find.

Info

One Damaged Upright Takes The Row

Racking fails progressively. A struck upright loses most of its capacity, and a collapse rarely stops at the bay it started in. Classification decides whether the bay is unloaded now or repaired later.

Single Choice

Inspection Level*

Scored

Visual by the area owner weekly, or expert inspection by a competent person yearly.

  • Expert inspection, competent person4 pts
  • Visual, area owner2 pts
Text

Run Reference*

Numeric Answer

Bays Inspected*

Single Choice

Racking Configuration

Optional
Adjustable pallet rackingDrive inPush backCantileverMobileShelving
Single Choice

Load Notice Displayed*

Scored

Bay and beam load limits must be on display. Without them nobody knows what safe looks like.

  • Yes3 pts
  • Faded or partial1 pt
  • No0 pts
Single Choice

Notice Matches Current Configuration*

Scored
  • Yes3 pts
  • Out of date0 pts

Structure

9 fields
Single Choice

Uprights Straight And Undamaged*

Scored
  • Yes3 pts
  • Minor damage1 pt
  • Significant0 pts
Single Choice

Bracing Intact*

Scored
  • Yes3 pts
  • Some damage1 pt
  • Missing0 pts
Single Choice

Baseplates Secure And Bolted*

Scored
  • Yes3 pts
  • Some loose1 pt
  • Unbolted0 pts
Single Choice

Beams Seated And Locked*

Scored
  • Yes3 pts
  • Some unlocked1 pt
  • No0 pts
Single Choice

Beam Deflection Within Limit*

Scored
  • Yes3 pts
  • Marginal1 pt
  • Exceeded0 pts
Single Choice

Beam Connector Locks Present*

Scored
  • All present3 pts
  • Some missing1 pt
  • Many missing0 pts
Single Choice

Row Spacers Fitted

OptionalScored
  • Yes3 pts
  • Some missing1 pt
  • No0 pts
Single Choice

Frame Protection Fitted*

Scored
  • Yes3 pts
  • Partial1 pt
  • None0 pts
Single Choice

Floor Condition At Baseplates*

Scored
  • Sound3 pts
  • Cracked1 pt
  • Failing0 pts

Loading

6 fields
Single Choice

Pallets Correctly Seated*

Scored
  • Yes3 pts
  • Some poorly seated1 pt
  • No0 pts
Single Choice

No Overhang Into Aisle*

Scored
  • Confirmed3 pts
  • Some1 pt
  • Significant0 pts
Single Choice

Loads Within Stated Limit*

Scored
  • Yes3 pts
  • Uncertain1 pt
  • Exceeded0 pts
Single Choice

Damaged Pallets In Racking*

Scored
  • None3 pts
  • Some1 pt
  • Many0 pts
Single Choice

Loose Items At Height*

Scored

Anything unsecured on a top beam falls into an aisle people walk down.

  • None3 pts
  • Some1 pt
  • Many0 pts
Single Choice

Netting Or Backstops Where Needed

OptionalScored
  • Yes3 pts
  • Not required3 pts
  • No0 pts

Damage found

Repeats8 fields
Text

Bay Or Location Reference*

Single Choice

Component Damaged*

UprightBeamBracingBaseplateGuard
Single Choice

Damage Classification*

Scored

Green means monitor, amber means repair within four weeks, red means unload the bay now.

  • Green, monitor3 pts
  • Amber, repair within period1 pt
  • Red, unload now0 pts
Text

Measurement Taken

Optional
File Upload

Photograph

Optional
Single Choice

Bay Unloaded Immediately

OptionalScoredShows if Damage Classification contains Red
  • Yes3 pts
  • No0 pts
Text

Damage Report ID

OptionalLinked

Links to SAF-132 Report ID

Text

Work Order ID

OptionalLinked

Links to MNT-002 Work Order ID

Summary

5 fields
Numeric Answer

Green Damage Found

Optional
Numeric Answer

Amber Damage Found*

Scored
Numeric Answer

Red Damage Found*

Scored
Single Choice

Repeat Damage At Same Location*

Scored

The same corner struck repeatedly is a layout or traffic problem, not an operator problem.

  • No3 pts
  • Yes0 pts
Text

Cause Pattern Identified

Optional

Related records

1 field
Text

Storage Location Register ID

OptionalLinked

The locations covered by this run.

Links to FDN-024 Register ID

Result

14 fields
Numeric Answer

Items Assessed*

Excludes anything marked N/A.

Numeric Answer

Items Failed*

Numeric Answer

Score Percent*

Scored

Calculated on submission. High is good. N/A items leave the denominator.

Single Choice

Result Band*

Scored
  • Pass3 pts
  • Caution1 pt
  • Fail0 pts
Numeric Answer

Completeness Percent*

How much of the template was actually answered. A high score on a half completed form is not a high score.

Single Choice

Action Required*

Scored

Raise the action record, then enter its reference here.

  • No2 pts
  • Yes0 pts
Single Choice

Priority

OptionalScoredShows if Action Required equals Yes
  • High0 pts
  • Medium1 pt
  • Low3 pts
Text

CAPA ID

OptionalLinkedShows if Action Required equals Yes

Format CAPA-2026-00000.

Links to FDN-014 CAPA ID

Users

Action Owner

OptionalShows if Action Required equals Yes
Date & Time

Next Due*

Users

Inspector*

Signature

Signature*

Users

Warehouse Manager*

Signature

Second Signature*

SAF-131 · record IDs look like INSP-2026-000 · Links Storage location register, Work orders

Open in Knowella

Run it with agents

From a document you fill in to a programme that runs itself

The inspection classifies damage. What fails is the amber list that aged past four weeks and the recurrence nobody mapped.

KnowSafe

Records the date damage was first noted and escalates amber to red automatically at four weeks, rather than carrying it as a status.

KnowMaintain

Turns classified damage into work orders with the timescale attached, and prevents reloading of offloaded locations until rectified.

Ella
Ella

Maps damage by location across inspections, so recurrence surfaces as a layout finding rather than as repeated repairs.

KnowLogistics

Links impacts to traffic flow and slot usage, and keeps load notices aligned with the current beam configuration.

This template lives in KnowSafe — safety and compliance. Incidents, hazards, permits, inspections and the critical controls behind them.

Meet KnowSafe→

Glossary

Racking Inspection definitions and key terms

SEMA
Storage Equipment Manufacturers' Association, publisher of the UK racking codes of practice and the risk classification system.
SARI
SEMA Approved Rack Inspector, a qualified external inspector for expert inspections.
PRRS
Person Responsible for Rack Safety, the trained internal role conducting routine inspections and receiving damage reports.
Red risk
Damage well beyond allowable limits requiring immediate offloading and isolation of the affected locations.
Amber risk
Damage exceeding allowable limits requiring offloading as soon as practicable, escalating to red if unrectified after four weeks.
Green risk
Damage within allowable limits, recorded and monitored at subsequent inspections and useful for identifying patterns.
Offloading
Removal of everything supported by the affected component, including levels above and adjacent bays where the damage warrants.
EN 15635
The European standard covering application and maintenance of static steel storage equipment, including damage assessment.

FAQ

Frequently asked questions about racking inspection

What does amber actually require?+

Offloading the affected location as soon as practicable, not reloading until the damage is rectified, and rectification within four weeks. Where four weeks pass without remedial work, the SEMA code says the damage should be treated as red risk requiring immediate offloading. Amber is an obligation with a deadline rather than a monitoring category.

How often should racking be inspected?+

Expert inspection by a competent inspector at least annually, and more frequently for high-volume or high-risk operations, supported by regular internal inspections by a trained person responsible for rack safety, and an immediate check after any impact. PUWER requires inspection at suitable intervals and after exceptional circumstances, which an impact is.

What does offloading involve?+

Removing everything supported by the affected component. For a damaged beam that is the load on that beam. For a damaged frame member it includes loads on levels above and, depending on the construction and the nature of the damage, adjacent bays. Where there is any doubt, clearing adjacent bays and seeking expert advice is the appropriate response.

Why do green findings matter?+

Because they show patterns. Damage within allowable limits is recorded and monitored rather than acted on individually, and its distribution across a warehouse points at aisle widths, turning circles, lighting or traffic flow. Green findings clustering in one area are the earliest available indication of a layout problem that will eventually produce amber and red ones.

What is most often missed?+

Load notices after reconfiguration. Moving beam levels changes the permitted load per level and per bay, and the notice on the end frame frequently still describes the original configuration. Alongside that, missing beam locks are routinely treated as cosmetic when a dislodged beam is a collapse mechanism.

Keep going

Related templates and programmes

Industries this is written for

Siddarth Singh

Written and reviewed by

Siddarth Singh

Founder & Chief Executive Officer, Knowella

Certified Safety Professional and industrial and systems engineer with more than a decade inside food supply chain, freight and manufacturing operations. This page was written against the current text of the standards it cites, not against secondary summaries of them.

  • Certified Safety Professional (CSP), Board of Certified Safety Professionals
  • MBA, University of Chicago Booth School of Business
  • MS and BS, The Ohio State University, Industrial and Systems Engineering
  • Six Sigma Black Belt
Verify with BCSP →

Sources and last review. Reviewed 16 August 2026 against:

  • SEMA codes of practice, including the red, amber and green risk classification and escalation rule
  • EN 15635, steel static storage systems, application and maintenance of storage equipment
  • HSE HSG76, warehousing and storage: a guide to health and safety (GB)
  • Provision and Use of Work Equipment Regulations 1998, regulations 4, 5 and 6 (GB)
  • 29 CFR 1910.176, handling materials, general, OSHA

This page is general guidance, not legal advice. Confirm requirements with your jurisdiction’s regulator.

Start in Minutes, Not Weeks

Launch a Ready-Made Template and Customize It Your Way

Every template is fully editable. Adjust fields, workflows, and branding to match your processes, then deploy to your team instantly.