Trench collapse is close to unsurvivable and almost entirely preventable, and the two facts together explain why enforcement here is unlike anywhere else in construction. A cubic yard of soil weighs around 3,000 pounds. It arrives in under a second, and it arrives on someone who was standing in a hole that a protective system sitting twenty feet away would have made safe.

KnowSafePermitSAF-052Pinned in navigation64 fields across 7 sectionsFull researchSee the form

Reviewed by Siddarth SinghCSPLast reviewed 16 August 2026

Basis
OSHA 1926 Subpart P
Workspace
KnowSafe
Form type
Permit
Protective system
Required at 5 feet
Inspection
Before each shift and after rain

The short version

  • Protective systems are required at five feet, and below that wherever a competent person sees potential for cave-in. Sloping, benching, shoring or shielding, selected against the soil type.
  • A competent person must inspect before each shift, as needed throughout the shift, and after every rainstorm or other hazard-increasing event. Daily is the floor, not the standard.
  • Excavated spoil and equipment must be kept at least two feet from the edge, because surcharge load at the lip is a direct contributor to wall failure.
  • A means of egress is required within 25 feet of lateral travel in trenches four feet or deeper. In a collapse the distance to a ladder is the distance to survival.
  • OSHA operates a National Emphasis Program for trenching and excavation and has stated it will consider criminal referrals where employer action or inaction kills a worker.
  • Penalties reflect that posture. In April 2026 OSHA proposed nearly $4.8 million across two fatal collapse cases, including $4,699,362 against a single contractor for 57 combined willful, repeat and serious violations.

What this is

What is an excavation permit?

What is an excavation permit?

An excavation permit is written authorisation to break ground, recording that buried services have been located, that the soil has been classified and a protective system selected, that spoil setback and access are arranged, that atmospheric and water hazards are controlled, and that a competent person has inspected before entry.

When is a protective system required?

For any trench five feet deep or greater under 29 CFR 1926.652, unless the excavation is made entirely in stable rock. Below five feet a protective system is still required where a competent person examining the ground finds indication of a potential cave-in, so the five-foot figure is a threshold rather than a safe depth.

Who is the competent person?

Someone capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous or dangerous, and who has authorisation to take prompt corrective measures. The authority to stop work is part of the definition, not an addition to it.

Scope

When is an excavation permit required?

The permit covers ground disturbance and the entry that follows it. Several related controls sit alongside rather than inside it.

Use this template when

  • Any excavation, trench, pit or ground disturbance where people may enter or work adjacent
  • Work near known or suspected buried services, whether or not anyone will enter
  • Excavation adjacent to existing structures, roads or previously disturbed ground
  • Work where atmospheric hazards are credible: near sewers, contaminated ground, landfill or fuel storage
  • Any excavation requiring a change of protective system as it deepens or as conditions change

Do not use it for

  • The confined space entry permit, which applies additionally where the excavation meets the definition of a permit space
  • Utility location itself, which is a separate survey activity referenced by the permit rather than performed by it
  • Traffic management and road opening approvals, which are their own permissions with their own authorities
  • The competent person's inspection record, which is a per-shift document generated under the permit
  • Ground investigation and design, which precede the work and inform the protective system selection

Compliance mapping

Which OSHA 1926 Subpart P requirements does this satisfy?

Excavation is one of the most prescriptive areas in construction regulation, because the failure mode is well understood and the controls are well established.

ClauseRequirementWhere it lands
1926.651(b)Utility installations located and, where reasonably practicable, supported or removed before excavationGate 1 Buried services
1926.652(a)(1)Protective system for excavations five feet or deeper, or at any depth with indication of potential cave-inGate 2 Excavation safety
1926.652(b)Sloping and benching designed in accordance with soil classification and the standard's appendicesGate 2 Excavation safety
1926.651(j)(2)Spoil, materials and equipment kept at least two feet from the edge, or retainedGate 2 Excavation safety
1926.651(c)(2)Means of egress within 25 feet of lateral travel in trenches four feet or deeperGate 2 Excavation safety
1926.651(k)(1)Competent person inspection before each shift, as needed during the shift, and after every rainstormAuthorisation
1926.651(g)(1)Atmospheric testing where hazardous atmosphere could reasonably be expected, deeper than four feetGate 3 Atmosphere and rescue
1926.651(g)(2)Emergency rescue equipment available where hazardous atmospheric conditions exist or may developGate 3 Atmosphere and rescue
1926.651(h)Protection from water accumulation, including removal and monitoring by a competent personGate 2 Excavation safety

What it does not cover

  • Confined space entry permit, required additionally where the excavation meets the permit space definition and the atmosphere or configuration warrants it.
  • Utility location survey, which is a separate activity whose results the permit records rather than produces.
  • Protective system design for excavations over twenty feet, which requires a registered professional engineer.
  • Traffic management and highway permissions, which are separate approvals from separate authorities.
  • The per-shift competent person inspection, which is generated under the permit and recorded per inspection rather than per excavation.

How to complete it

How to complete an excavation permit, step by step

An excavation permit is a sequence of gates, each of which corresponds to a recurring fatality mechanism.

Locate services, then prove the location

Drawings are a starting point and are frequently wrong, particularly on sites with a long history of alterations. Detection survey, then careful hand digging or vacuum excavation to expose the service, then physical marking. Strike incidents almost always trace to a drawing that was trusted rather than verified, and the consequence ranges from an outage to an explosion.

Classify the soil and record who did it

The protective system selection depends on soil type, and soil type is a competent person judgement made on site with a manual and visual test. Recording the classification and the person who made it turns the protective system from an assumption into a decision with reasoning behind it, which is what an investigator will look for.

Record the inspection per shift, not per excavation

The requirement is before each shift, as conditions warrant during the shift, and after every rainstorm or other hazard-increasing event. A single inspection at the start of a week-long job does not satisfy it. Rain is the trigger most often missed, and it is the one most closely associated with collapse.

Check the setback and the egress physically

Spoil migrates toward the edge as the day goes on, and equipment gets parked where it is convenient. Both add surcharge load at the point where the wall is weakest. Egress within 25 feet of lateral travel means a ladder that is present, secured and extends above the surface, not one that was there this morning.

What auditors find

Most common excavation permit findings

Excavation findings are notable for how consistently they involve the total absence of a control rather than an inadequate one.

FindingClauseWhat fixes it
No protective system in a trench five feet or deeper.1926.652(a)(1)Nothing enters the trench until the system is installed; this is the mechanism in nearly every fatality.
Protective system available on site but not installed.1926.652(a)(1)Make installation a gate on the permit, verified physically before entry is authorised.
No competent person inspection before the shift, or no record of one.1926.651(k)(1)Record per shift with the inspector named; a per-excavation record does not satisfy the standard.
No inspection after rainfall despite conditions changing.1926.651(k)(1)Make weather an explicit trigger; rain is strongly associated with subsequent collapse.
Spoil or equipment within two feet of the edge.1926.651(j)(2)Mark the setback physically; spoil migrates during the day and nobody notices.
No ladder or ramp within 25 feet of lateral travel.1926.651(c)(2)Position egress before entry; in a collapse the distance to a ladder decides the outcome.
Services struck because drawings were relied on without verification.1926.651(b)Detect, expose and mark; drawings are an input, not a location.
Atmosphere not tested where a hazardous atmosphere could reasonably be expected.1926.651(g)(1)Test where the excavation is over four feet and the ground or surroundings suggest risk.
Soil classification not performed or not recorded, so system selection has no basis.1926.652(b)Record the classification, the test used and the person who made it.
Excavation over twenty feet without a protective system designed by a professional engineer.1926.652(b)(4)Engineered design is mandatory above twenty feet, not a matter of preference.

Case in point

Case in point: the shield beside the trench

In June 2022 two workers aged twenty and thirty-nine were killed in Jarrell, Texas, when an unprotected trench more than twenty feet deep collapsed on them. Trench shields that could have saved them were on site, sitting unused beside the excavation.

That case became part of the impetus for OSHA's enhanced enforcement posture on trenching, including the statement that it would consider criminal referrals where employer action or inaction kills a worker, and a commitment to more than a thousand random trench inspections nationwide under its National Emphasis Program.

The pattern has not changed since. In April 2026 OSHA announced two fatal collapse cases with nearly $4.8 million in combined proposed penalties, one of them $4,699,362 against a single contractor for 57 willful, repeat and serious violations. In both, workers had been sent into unprotected trenches.

The template

The template, field by field

The form exactly as it installs. Every field, option, score and conditional rule is editable, and the links to other templates come with it.

64fields
7 sections
Reference
SAF-052
Archetype
Permit
Record ID
PTW-2026-000
Scoring
Go or no go
Direction
n/a
Singleton
No
Basis
OSHA 1926 Subpart P
Links
Links Site; feeds Rescue Plan
Tags
Permit, Excavation
Sections
7
Fields
64
Follow up fields
7
Repeating sections
0
Links out
8
Field typesOwn ID, generated on saveCase thread and parentPick list from a registryLinked to another templateFollow up, dashed outlineScored

Permit

9 fields
Text

Permit ID*

Generated on save

Auto sequence. Format PTW-2026-00000.

The record's own ID. Other templates point at this value.

Single Choice

Status*

Scored

Drives who this goes to next.

  • Planned2 pts
  • In progress2 pts
  • Complete3 pts
  • Deferred0 pts
  • Open0 pts
  • Closed3 pts
  • Overdue0 pts
Date & Time

Valid From*

Date & Time

Valid To*

One shift maximum. A new permit is raised for the next shift.

Info

Before You Start

Every excavation starts with finding out what is already buried there. Drawings alone are not enough.

Pick List

Site*

From FDN-001 Site NameFilter: Status is Active
Text

Site ID*

Linked

Format SITE-000.

Links to FDN-001 Site ID

Single Choice

Area*

The area within the site.

Cutting roomBoning hallPackingChill storeFreezerPasteurisingFillingCulture roomDespatchYardWorkshopPlant roomOffices
Location

Exact Location

Optional

Drop a pin for anything hard to find.

The work

12 fields
Text

Work Description*

Text

Work Order ID

OptionalLinked

Links to MNT-002 Work Order ID

Numeric Answer

Number Of Workers*

Pick List

Asset

OptionalFrom FDN-002 Asset NameFilter: Site matches
Text

Asset ID

OptionalLinked

Format AST-0000.

Links to FDN-002 Asset ID

Pick List

Risk Assessment

OptionalFrom FDN-012 Risk Title
Text

Risk ID

OptionalLinked

Format RSK-2026-00000.

Links to FDN-012 Risk ID

Single Choice

Contractor Involved*

NoYes
Pick List

Contractor

OptionalFrom FDN-005 Vendor NameShows if Contractor Involved equals YesFilter: Status is Approved
Text

Vendor ID

OptionalLinkedShows if Contractor Involved equals Yes

Format VEN-0000.

Links to FDN-005 Vendor ID

Single Choice

Induction Verified

OptionalScoredShows if Contractor Involved equals Yes
  • Yes2 pts
  • No0 pts
  • N/Aexcluded from denominator
Single Choice

Method Statement Received

OptionalScoredShows if Contractor Involved equals Yes
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator

Gate 1 Buried services

6 fields
Single Choice

Service Drawings Obtained*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Single Choice

Cable And Pipe Locate Completed*

Scored
  • Yes2 pts
  • No0 pts
  • N/Aexcluded from denominator
Single Choice

Locate Marks On Ground*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
File Upload

Locate Certificate Attached

Optional
Single Choice

Trial Holes Hand Dug*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Multi Choice

Services Identified

OptionalScored

Electrical, gas, water, effluent, ammonia, glycol, data.

  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator

Gate 2 Excavation safety

10 fields
Numeric Answer

Depth Metres*

Scored
Single Choice

Ground Type*

Scored
  • Firm cohesive3 pts
  • Mixed2 pts
  • Loose or granular1 pt
  • Previously disturbed0 pts
Single Choice

Water Table Considered*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Single Choice

Support Method*

Scored

Battering, shoring or trench box. Unsupported excavations collapse without warning.

  • Battering or benching3 pts
  • Trench box3 pts
  • Shoring3 pts
  • None, under 1.2 metres1 pt
Single Choice

Support Installed Before Entry*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Single Choice

Safe Access And Egress Provided*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Single Choice

Spoil Set Back From Edge*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Single Choice

Edge Protection Installed*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Single Choice

Plant Kept Clear Of Edge*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Single Choice

Adjacent Structures Assessed*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator

Gate 3 Atmosphere and rescue

4 fields
Single Choice

Confined Space Conditions Possible*

Scored

Deep excavations can accumulate gas and become confined spaces.

  • No3 pts
  • Yes0 pts
Text

Confined Space Permit ID

OptionalLinkedShows if Confined Space Conditions Possible equals Yes

Links to SAF-049 Permit ID

Text

Rescue Plan ID*

Linked

Links to SAF-103 Plan ID

Single Choice

Daily Reinspection Scheduled*

Scored

Excavations are reinspected after rain, frost and any nearby plant movement.

  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator

Authorisation

11 fields
Info

No Gate, No Start

Every gate above must pass before work begins. There is no partial permit. If anything is unresolved, the permit is not issued.

Single Choice

All Gates Passed*

Scored
  • Yes2 pts
  • No, entry refused0 pts
Text

Reason Not Issued

OptionalShows if All Gates Passed not equals Yes
Users

Issued By*

Single Choice

Issuer Authorised For This Permit*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Signature

Issuer Signature*

Date & Time

Issue Time*

Users

Accepted By*

Signature

Acceptor Signature*

Single Choice

Toolbox Talk Held With Crew*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Text

Talk Record ID

OptionalLinked

Links to TRN-009 Talk ID

Closure

12 fields
Single Choice

Work Complete*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Work Suspended

OptionalShows if Work Complete equals No
YesNo
Single Choice

All Persons Accounted For*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Single Choice

Tools And Equipment Removed*

Scored
  • Yes2 pts
  • No0 pts
  • N/Aexcluded from denominator
Single Choice

Area Left Safe*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Single Choice

Guards And Controls Restored*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Excavation Backfilled Or Made Safe*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Single Choice

Surface Reinstated*

Scored
  • Pass2 pts
  • Partial1 pt
  • Fail0 pts
  • N/Aexcluded from denominator
Date & Time

Permit Cancelled Time*

Users

Cancelled By*

Signature

Closure Signature*

Signature

Area Owner Signature*

SAF-052 · record IDs look like PTW-2026-000 · Links Site; feeds Rescue Plan

Open in Knowella

Run it with agents

From a document you fill in to a programme that runs itself

The permit is a set of gates. What fails is the gap between the system being available and being installed, and the inspection that was performed once for a job that ran all week.

KnowSafe

Issues the permit against gates that must be physically verified, holds the per-shift inspection requirement, and reopens the inspection automatically after recorded rainfall.

KnowContractor

Verifies competent person qualification and contractor competency before a permit is issued, and links the permit to named individuals rather than to a company.

Ella
Ella

Cross-references interacting permits where the excavation is also a confined space, and holds them open and closed together.

KnowMaintain

Connects the excavation to the asset and the buried services register, so a strike updates the record that the next crew will rely on.

This template lives in KnowSafe — safety and compliance. Incidents, hazards, permits, inspections and the critical controls behind them.

Meet KnowSafe→

Glossary

Excavation Permit definitions and key terms

Competent person
Someone able to identify existing and predictable hazards and authorised to take prompt corrective measures, including stopping work.
Protective system
Sloping, benching, shoring or shielding used to prevent cave-in, selected against soil classification and depth.
Soil classification
Stable rock, Type A, B or C, determined by a competent person using manual and visual tests, governing the system selected.
Surcharge load
Weight applied near the excavation edge from spoil, equipment or vehicles, which increases the force on the wall.
Spoil setback
The minimum two feet between excavated material and the edge, required to limit surcharge and prevent material falling in.
Benching
Cutting the sides into horizontal steps with vertical faces between. Not permitted in Type C soil.
Shielding
A trench box or shield protecting workers from cave-in without preventing the collapse itself.
Hazard-increasing event
Rain, vibration, adjacent excavation, water accumulation or any change requiring a fresh competent person inspection.

FAQ

Frequently asked questions about excavation permit

At what depth is a protective system required?+

Five feet or deeper under 1926.652(a)(1), unless the excavation is entirely in stable rock. Below five feet a system is still required where a competent person finds indication of a potential cave-in. Fatalities have occurred in trenches shallower than five feet, so the figure is a mandatory threshold rather than a depth at which the ground becomes safe.

How often must the excavation be inspected?+

By a competent person before each shift, as needed throughout the shift, and after every rainstorm or other hazard-increasing event. The record should be per inspection rather than per excavation, which is a common gap: a job running a week generates one inspection record where it should generate five or more.

How far must spoil be kept from the edge?+

At least two feet, or it must be retained by a device sufficient to prevent it falling in. The setback also limits surcharge load on the wall. In practice spoil migrates toward the edge through the day and equipment is parked where convenient, which is why marking the line physically works better than stating it.

Do we always need to test the atmosphere?+

Where a hazardous atmosphere exists or could reasonably be expected in excavations deeper than four feet: near landfill, contaminated ground, sewers, fuel storage or where hazardous substances are stored nearby. Where atmospheric hazards exist or may develop, emergency rescue equipment must be available and attended.

What is OSHA's enforcement posture on trenching?+

Markedly more aggressive than in most areas. There is a standing National Emphasis Program, compliance officers may inspect any excavation site they encounter, and OSHA has stated it will consider criminal referrals where employer acts or omissions kill workers. Penalty levels reflect this: in April 2026 two fatal collapse cases drew nearly $4.8 million in proposed penalties combined.

When is an engineer required?+

Protective systems for excavations deeper than twenty feet must be designed by a registered professional engineer. Tabulated data may be used below that depth within its stated limits, but those limits are specific and using tabulated data outside its scope leaves the system without a valid design basis.

Keep going

Related templates and programmes

Siddarth Singh

Written and reviewed by

Siddarth Singh

Founder & Chief Executive Officer, Knowella

Certified Safety Professional and industrial and systems engineer with more than a decade inside food supply chain, freight and manufacturing operations. This page was written against the current text of the standards it cites, not against secondary summaries of them.

  • Certified Safety Professional (CSP), Board of Certified Safety Professionals
  • MBA, University of Chicago Booth School of Business
  • MS and BS, The Ohio State University, Industrial and Systems Engineering
  • Six Sigma Black Belt
Verify with BCSP →

Sources and last review. Reviewed 16 August 2026 against:

This page is general guidance, not legal advice. Confirm requirements with your jurisdiction’s regulator.