Knowella

Downtime Record

The recurring failure here is logging one total duration and one tidy reason, then closing the record. That number can't be trended, because it hides whether the plant was waiting on parts, waiting on a diagnosis, or genuinely being repaired, and it can't be defended, because planned changeovers and unplanned failures end up in the same bucket, flattering both.

KnowMaintainRecordMNT-011Pinned in navigation38 fields across 4 sectionsFull researchSee the form

Reviewed by Siddarth SinghCSPLast reviewed 16 August 2026

Basis
ISO 55001 cl.9.1
Workspace
KnowMaintain
Form type
Record
Review trigger
The moment the asset returns to service, not a later reconstruction
Completed by
Production and maintenance together, both signing

The short version

  • Downtime is only useful as a metric once planned and unplanned causes are separated; a combined total hides both the reliability signal and the scheduling discipline.
  • The template breaks a single duration into notify, respond, diagnose, wait-for-parts, repair and restart phases, because each phase has a different owner and a different fix.
  • Production impact (units lost, orders affected) and a joint production-plus-maintenance signature are required, because the figure is disputed more often than it's accepted at face value.
  • Scoring runs on downtime hours, and it is deliberately punitive on unplanned time and lenient on planned time, so the number can't be gamed by scheduling more planned stops.

What this is

What is a downtime record?

What is a downtime record?

It is the record that captures exactly when an asset stopped producing, when it started again, and why. It sits inside KnowMaintain's Planned Maintenance programme and is built against ISO 55001 cl.9.1, the monitoring and measurement clause that requires performance to be tracked against defined criteria.

Why split planned from unplanned downtime?

Planned downtime (changeovers, cleaning, scheduled stops) and unplanned downtime (failures) have different causes, different owners and different fixes. Merging them into one duration figure produces an availability number that goes up when you schedule more stoppages, which is the opposite of what the metric should reward.

How is a downtime record different from a work order?

A work order describes the job done to fix or maintain an asset. A downtime record describes the outage itself — its duration, its cause and its production impact — and may reference a work order without being one. A single failure can generate both.

Scope

When is a downtime record required?

This record exists to measure one outage, precisely, from stop to restart. It is not the place to plan the repair, request the parts, or review the trend — those are separate steps in the same programme, and folding them in here is what makes downtime data impossible to report on later.

Use this template when

  • An asset has stopped producing, whether the stop was planned or a failure
  • The asset has now returned to service and the full duration is known
  • A new record is needed; each one gets its own ID in the form DT-2026-000
  • A failure report or work order needs a downtime figure attached to it
  • Production and maintenance need a jointly-agreed number before either side reports it upward

Do not use it for

  • Maintenance Request, which asks maintenance to look at a problem before there is a confirmed stoppage to time.
  • Work Order, which plans and records the repair itself, not the outage duration around it.
  • Corrective Work Order, which documents the fix for a failure that has already been logged as downtime here.
  • Backlog Review, which looks at outstanding work orders in aggregate, not a single timed event.
  • Anything outside KnowMaintain, which belongs in the workspace that owns that process.

Compliance mapping

Which ISO 55001 cl.9.1 requirements does this satisfy?

ISO 55001 doesn't prescribe a downtime form, but its performance evaluation clause requires asset performance to be monitored against criteria the organisation has itself defined — and several supporting clauses shape what that measurement has to look like in practice.

ClauseRequirementWhere it lands
ISO 55001 cl.9.1Asset performance must be monitored, measured and evaluated against defined criteria at defined intervals.The downtime
ISO 55001 cl.9.1The method of measurement must be capable of producing valid, comparable results — which is why duration is broken into named phases rather than left as one figure.Time breakdown
ISO 55001 cl.8.1Operational controls must distinguish planned activity from unplanned deviation so the two can be managed separately.The downtime
ISO 55001 cl.7.5Information determined necessary for the effectiveness of the asset management system must be controlled and retained, with each record uniquely identifiable.Header
ISO 55001 cl.6.1Risks and opportunities affecting asset management objectives must be identified — production impact is the input that feeds that risk view.Impact
ISO 55001 cl.5.3Responsibilities for reporting on asset management performance must be assigned and understood, which is why the record needs both a production and a maintenance signature.Impact
ISO 55001 cl.10.1Nonconformities identified through monitoring must be linked forward to correction and corrective action rather than left as a standalone figure.The downtime

What it does not cover

  • Duration Hours, which is filled in but stands alone, with every phase field in Time breakdown left blank.
  • Downtime Type, which is left unset or defaulted, so planned and unplanned events can't be separated in reporting.
  • Signature and Second Signature, which are missing, leaving the figure agreed by only one side of the plant.
  • Reason Detail, which repeats the Reason Category verbatim instead of describing what actually happened.
  • Production Impact Record ID, which is absent even though Orders Affected is marked Significant.

Global

Downtime Record requirements by country

ISO 55001 is a voluntary management-systems standard, so its pull comes from certification schemes and customer contracts rather than statute — but the weight of that pull varies sharply by market.

United Kingdom

ISO 55001:2014, developed from the Institute of Asset Management's PAS 55

The UK originated the asset-management-system approach through PAS 55 before it became ISO 55001, so UK-based utilities, rail and process industries treat downtime records as baseline evidence for certification audits.

A downtime record with no phase breakdown and no joint sign-off is the kind of gap a UKAS-accredited auditor will flag as a monitoring nonconformity, not a paperwork nicety.

United States

No federal mandate; ISO 55001 adoption is customer- or insurer-driven

There is no US regulatory requirement to run an ISO 55001 asset management system, so the record's authority in an American plant comes from customer audit clauses, insurance loss-control requirements, or corporate reliability programmes rather than law.

Skipping the joint signature or the phase breakdown carries no statutory exposure, but it does undermine the record the plant would otherwise use to negotiate insurance premiums or defend an OEE claim to a customer.

International supply chains

ISO 55001:2014 certification and ISO 55000:2014 terminology

Multinational buyers increasingly ask suppliers to show a functioning asset management system as part of vendor qualification, and downtime data is one of the few artefacts an auditor can sample and cross-check against maintenance and production records independently.

A downtime record that can't be reconciled against the linked work order or failure report undermines the whole system's credibility in a supplier audit, not just this one record.

How to complete it

How to complete a downtime record, step by step

Filling in every field is mechanical. The judgement calls are in deciding what the numbers actually mean before they're signed off.

Where the clock starts

Start Time should be the moment the asset stopped producing, not the moment someone noticed. If Time To Notify is consistently zero across records, that's a sign the clock is being started late rather than the plant genuinely having no detection lag — and it will understate true downtime every time.

Whether waiting-for-parts counts as downtime or as a planning failure

Time Waiting For Parts Minutes belongs in this record because the asset genuinely wasn't running, but a plant that lets this figure dominate repeatedly has a spares-holding problem, not a maintenance-response problem. Routing that pattern to Critical Spares Review rather than absorbing it silently here is the call that keeps the two records honest.

How multi-line impact gets apportioned

When Line Affected is Multiple, Units Lost and Product Lost need to reflect the combined impact, not one line's figure copied across. Under-recording here because the split is awkward to calculate is the single most common way this template quietly understates cost.

When a downtime record needs its own failure report

Not every stoppage warrants a Failure Report ID — a changeover overrun doesn't — but an unplanned failure with a mechanical or electrical Reason Category almost always should carry one, because the downtime record times the event while the failure report investigates the cause.

What auditors find

Most common downtime record findings

The gaps that recur in downtime records tend to fall in the same six places, almost always because the record was closed for speed rather than for accuracy.

FindingClauseWhat fixes it
Duration Hours is populated but every Time breakdown field is blank.ISO 55001 cl.9.1Require at minimum Time To Respond and Time To Repair before a record can move to Complete, so the total can be decomposed later even if not every phase was timed live.
Downtime Type defaults to Unplanned regardless of what actually happened.ISO 55001 cl.8.1Remove any default on Downtime Type and require an explicit choice, since a default that always fires the same way is functionally the same as not asking the question.
Reason Category is set but Reason Detail just restates the category.ISO 55001 cl.9.1Add a minimum character check or a prompt asking what specifically failed, so Reason Detail carries information the category alone doesn't.
Only one of the two required signatures is present at Complete.ISO 55001 cl.5.3Block the status transition to Complete until both Production and Maintenance signatures are captured, matching the joint-ownership design of the record.
Orders Affected is marked Significant with no Production Impact Record ID linked.ISO 55001 cl.6.1Make the link field conditionally required whenever Orders Affected is Some or Significant, so the downstream impact record actually gets created.
Work Order ID and Failure Report ID are both left blank on unplanned events.ISO 55001 cl.10.1Require at least one of the two links whenever Downtime Type is Unplanned, so the corrective loop is traceable from the downtime figure forward.

Case in point

Case in point: the four-hour stoppage that was really three different problems

A packing line stopped for four hours and the shift log recorded one Downtime Record: Reason Category 'Mechanical failure', Duration Hours 4, Status Complete. On paper it looked like a routine repair. The phase fields, filled in only after a supervisor pushed back, told a different story: eleven minutes to notice the stop, forty minutes to get a technician on site, ninety minutes waiting for a bearing that wasn't in the local store, and only fifty minutes of actual repair.

None of those numbers pointed at maintenance competence. They pointed at a parts-holding gap and a response-time gap that a single four-hour total had completely absorbed. Once the record carried the breakdown, the ninety-minute wait routed into a Critical Spares Review instead of counting against the technician's average repair time — which is the difference between fixing the actual constraint and re-training someone for a problem they didn't cause.

The template

The template, field by field

The form exactly as it installs. Every field, option, score and conditional rule is editable, and the links to other templates come with it.

38fields
4 sections
Reference
MNT-011
Archetype
Record
Record ID
DT-2026-000
Scoring
Downtime hours
Direction
High is bad
Singleton
No
Basis
ISO 55001 cl.9.1
Links
Links Asset, Breakdown
Tags
Maintenance, Reliability
Sections
4
Fields
38
Follow up fields
0
Repeating sections
0
Links out
5
Field typesOwn ID, generated on saveCase thread and parentPick list from a registryLinked to another templateFollow up, dashed outlineScored

Header

14 fields
Text

Record ID*

Generated on save

Auto sequence. Format DT-2026-0000.

The record's own ID. Other templates point at this value.

Single Choice

Status*

Scored

Drives who this goes to next.

  • Planned2 pts
  • In progress2 pts
  • Complete3 pts
  • Deferred0 pts
  • Open0 pts
  • Closed3 pts
  • Overdue0 pts
Date & Time

Date and Time*

Users

Raised By*

Pick List

Site*

From FDN-001 Site NameFilter: Status is Active
Text

Site ID*

Linked

Format SITE-000.

Links to FDN-001 Site ID

Single Choice

Area

Optional

The area within the site.

Cutting roomBoning hallPackingChill storeFreezerPasteurisingFillingCulture roomDespatchYardWorkshopPlant roomOffices
Location

Exact Location

Optional

Drop a pin for anything hard to find.

Pick List

Asset*

From FDN-002 Asset NameFilter: Site matches, Status is Active
Text

Asset ID*

Linked

Format AST-0000.

Links to FDN-002 Asset ID

Text

Case ID

OptionalThread key

Copy from the record that triggered this work.

Thread key. Every record in this chain carries this value

Single Choice

Parent Type

Optional

What kind of record this follows.

IncidentNear missFindingAuditInspectionRisk assessmentComplaintEquipment failureNonconformanceManagement of change
Text

Parent ID

OptionalThread key

The reference of that record.

Immediate predecessor record

Date & Time

Raised Date*

The downtime

8 fields
Single Choice

Downtime Type*

Scored

Planned and unplanned downtime behave completely differently. Never combine them.

  • Planned3 pts
  • Unplanned0 pts
Date & Time

Start Time*

Date & Time

End Time*

Numeric Answer

Duration Hours*

Scored
Single Choice

Reason Category*

Mechanical failureElectrical failureControl systemUtility failureChangeoverCleaningMaterial shortageOperator error
Text

Reason Detail*

Text

Work Order ID

OptionalLinked

Links to MNT-002 Work Order ID

Text

Failure Report ID

OptionalLinked

Links to MNT-013 Case ID

Time breakdown

7 fields
Info

Where The Hours Actually Go

Time to respond, time to diagnose and time to repair are separate problems with separate fixes. Recording one total hides all three.

Numeric Answer

Time To Notify Minutes

OptionalScored
Numeric Answer

Time To Respond Minutes

OptionalScored
Numeric Answer

Time To Diagnose Minutes

OptionalScored
Numeric Answer

Time Waiting For Parts Minutes

OptionalScored
Numeric Answer

Time To Repair Minutes

OptionalScored
Numeric Answer

Time To Restart Minutes

OptionalScored

Impact

9 fields
Single Choice

Line Affected*

Line 1Line 2Line 3Line 4Line 5Multiple
Numeric Answer

Units Lost

OptionalScored
Numeric Answer

Product Lost

OptionalScored
Single Choice

Orders Affected

OptionalScored
  • None3 pts
  • Some1 pt
  • Significant0 pts
Text

Production Impact Record ID

OptionalLinked

Links to MNT-018 Record ID

Users

Production*

Signature

Signature*

Users

Maintenance*

Signature

Second Signature*

MNT-011 · record IDs look like DT-2026-000 · Links Asset, Breakdown

Open in Knowella

Run it with agents

From a document you fill in to a programme that runs itself

The form captures the event. What actually determines whether the number gets used is whether it's routed, checked and rolled up before anyone needs it for a decision.

KnowMaintain

Holds the downtime library against the asset register and work order history, flags records missing a phase breakdown or a second signature, and keeps the link to backlog and spares data live.

KnowQuality

Picks up the production-impact fields — units lost, orders affected — and folds them into the same nonconformance view that food safety and customer complaint data already feed.

KnowSafe

Watches for downtime events on assets already flagged as safety- or food-safety-critical, and escalates a pattern of unplanned stoppages before it becomes an incident.

Ella
Ella

Chases the missing signature or the blank phase field, rolls this period's downtime hours into one view against the trend, and holds every write for approval before it touches a record.

This template lives in KnowMaintain — asset maintenance. Work orders, planned maintenance, calibration, reliability and shutdowns.

Meet KnowMaintain→

Glossary

Downtime Record definitions and key terms

Planned downtime
A stoppage scheduled in advance — a changeover, a clean, a planned shutdown — that is expected and does not indicate a reliability problem on its own.
Unplanned downtime
A stoppage caused by an unexpected failure or condition, the category that drives reliability metrics and warrants root-cause investigation.
Time to diagnose
The interval between a technician arriving at the asset and identifying the specific cause of the stoppage, distinct from the time spent actually repairing it.
MTTR
Mean time to repair — the average duration of the repair phase alone across a set of downtime events, one of the figures this record's phase breakdown makes possible to calculate.
Ready backlog
Outstanding work that has parts, permits and a plan already in place, as distinct from work still waiting on one of those — the concept that links a downtime event's Work Order ID forward into backlog reporting.

FAQ

Frequently asked questions about downtime record

Does every stoppage need a downtime record?+

Any stoppage long enough to matter for reporting should get one, but very short micro-stops on a line with its own stop-log are usually aggregated separately rather than raised individually here — check how your plant has drawn that line before assuming every stop qualifies.

Who signs the downtime record?+

Both a production representative and a maintenance representative sign. The record is deliberately built as a joint artefact so the duration and cause aren't disputed after the fact by either side.

What happens if the phase times don't add up to the total duration?+

Some slack is normal — phases can overlap slightly, or a small gap can go unrecorded — but a large mismatch usually means Start Time or End Time was estimated after the fact rather than logged live, and it's worth correcting before the record is signed off.

Can a downtime record exist without a linked work order?+

Yes, for planned downtime like a changeover or clean-down that never needed one. For unplanned downtime, the absence of a linked work order or failure report is usually a sign the corrective loop was never closed.

How does this differ from an OEE calculation?+

This record is the raw input, not the calculation. OEE and availability figures are built by aggregating downtime records over a period; the record itself just needs to be accurate and correctly categorised for that aggregation to mean anything.

Why is Case ID optional if the record follows an incident?+

Not every downtime event follows a prior incident, near miss or finding — many are simply mechanical failures with no upstream trigger record. Case ID is there to thread the two together when one exists, not to force a link that doesn't.

Keep going

Related templates and programmes

Siddarth Singh

Written and reviewed by

Siddarth Singh

Founder & Chief Executive Officer, Knowella

Certified Safety Professional and industrial and systems engineer with more than a decade inside food supply chain, freight and manufacturing operations. This page was written against the current text of the standards it cites, not against secondary summaries of them.

  • Certified Safety Professional (CSP), Board of Certified Safety Professionals
  • MBA, University of Chicago Booth School of Business
  • MS and BS, The Ohio State University, Industrial and Systems Engineering
  • Six Sigma Black Belt
Verify with BCSP →

Sources and last review. Reviewed 16 August 2026 against:

  • ISO 55001:2014 cl.9.1 — Monitoring, measurement, analysis and evaluation
  • ISO 55001:2014 cl.8.1 — Operational planning and control
  • ISO 55001:2014 cl.7.5 — Documented information
  • ISO 55000:2014 — Asset management: Overview, principles and terminology

This page is general guidance, not legal advice. Confirm requirements with your jurisdiction’s regulator.

Start in Minutes, Not Weeks

Launch a Ready-Made Template and Customize It Your Way

Every template is fully editable. Adjust fields, workflows, and branding to match your processes, then deploy to your team instantly.