What this is
What is a downtime record?
What is a downtime record?
It is the record that captures exactly when an asset stopped producing, when it started again, and why. It sits inside KnowMaintain's Planned Maintenance programme and is built against ISO 55001 cl.9.1, the monitoring and measurement clause that requires performance to be tracked against defined criteria.
Why split planned from unplanned downtime?
Planned downtime (changeovers, cleaning, scheduled stops) and unplanned downtime (failures) have different causes, different owners and different fixes. Merging them into one duration figure produces an availability number that goes up when you schedule more stoppages, which is the opposite of what the metric should reward.
How is a downtime record different from a work order?
A work order describes the job done to fix or maintain an asset. A downtime record describes the outage itself — its duration, its cause and its production impact — and may reference a work order without being one. A single failure can generate both.
Scope
When is a downtime record required?
This record exists to measure one outage, precisely, from stop to restart. It is not the place to plan the repair, request the parts, or review the trend — those are separate steps in the same programme, and folding them in here is what makes downtime data impossible to report on later.
Use this template when
- An asset has stopped producing, whether the stop was planned or a failure
- The asset has now returned to service and the full duration is known
- A new record is needed; each one gets its own ID in the form DT-2026-000
- A failure report or work order needs a downtime figure attached to it
- Production and maintenance need a jointly-agreed number before either side reports it upward
Do not use it for
- Maintenance Request, which asks maintenance to look at a problem before there is a confirmed stoppage to time.
- Work Order, which plans and records the repair itself, not the outage duration around it.
- Corrective Work Order, which documents the fix for a failure that has already been logged as downtime here.
- Backlog Review, which looks at outstanding work orders in aggregate, not a single timed event.
- Anything outside KnowMaintain, which belongs in the workspace that owns that process.
Compliance mapping
Which ISO 55001 cl.9.1 requirements does this satisfy?
ISO 55001 doesn't prescribe a downtime form, but its performance evaluation clause requires asset performance to be monitored against criteria the organisation has itself defined — and several supporting clauses shape what that measurement has to look like in practice.
| Clause | Requirement | Where it lands |
|---|---|---|
| ISO 55001 cl.9.1 | Asset performance must be monitored, measured and evaluated against defined criteria at defined intervals. | The downtime |
| ISO 55001 cl.9.1 | The method of measurement must be capable of producing valid, comparable results — which is why duration is broken into named phases rather than left as one figure. | Time breakdown |
| ISO 55001 cl.8.1 | Operational controls must distinguish planned activity from unplanned deviation so the two can be managed separately. | The downtime |
| ISO 55001 cl.7.5 | Information determined necessary for the effectiveness of the asset management system must be controlled and retained, with each record uniquely identifiable. | Header |
| ISO 55001 cl.6.1 | Risks and opportunities affecting asset management objectives must be identified — production impact is the input that feeds that risk view. | Impact |
| ISO 55001 cl.5.3 | Responsibilities for reporting on asset management performance must be assigned and understood, which is why the record needs both a production and a maintenance signature. | Impact |
| ISO 55001 cl.10.1 | Nonconformities identified through monitoring must be linked forward to correction and corrective action rather than left as a standalone figure. | The downtime |
What it does not cover
- Duration Hours, which is filled in but stands alone, with every phase field in Time breakdown left blank.
- Downtime Type, which is left unset or defaulted, so planned and unplanned events can't be separated in reporting.
- Signature and Second Signature, which are missing, leaving the figure agreed by only one side of the plant.
- Reason Detail, which repeats the Reason Category verbatim instead of describing what actually happened.
- Production Impact Record ID, which is absent even though Orders Affected is marked Significant.
Global
Downtime Record requirements by country
ISO 55001 is a voluntary management-systems standard, so its pull comes from certification schemes and customer contracts rather than statute — but the weight of that pull varies sharply by market.
ISO 55001:2014, developed from the Institute of Asset Management's PAS 55
The UK originated the asset-management-system approach through PAS 55 before it became ISO 55001, so UK-based utilities, rail and process industries treat downtime records as baseline evidence for certification audits.
A downtime record with no phase breakdown and no joint sign-off is the kind of gap a UKAS-accredited auditor will flag as a monitoring nonconformity, not a paperwork nicety.
No federal mandate; ISO 55001 adoption is customer- or insurer-driven
There is no US regulatory requirement to run an ISO 55001 asset management system, so the record's authority in an American plant comes from customer audit clauses, insurance loss-control requirements, or corporate reliability programmes rather than law.
Skipping the joint signature or the phase breakdown carries no statutory exposure, but it does undermine the record the plant would otherwise use to negotiate insurance premiums or defend an OEE claim to a customer.
ISO 55001:2014 certification and ISO 55000:2014 terminology
Multinational buyers increasingly ask suppliers to show a functioning asset management system as part of vendor qualification, and downtime data is one of the few artefacts an auditor can sample and cross-check against maintenance and production records independently.
A downtime record that can't be reconciled against the linked work order or failure report undermines the whole system's credibility in a supplier audit, not just this one record.
How to complete it
How to complete a downtime record, step by step
Filling in every field is mechanical. The judgement calls are in deciding what the numbers actually mean before they're signed off.
Start Time should be the moment the asset stopped producing, not the moment someone noticed. If Time To Notify is consistently zero across records, that's a sign the clock is being started late rather than the plant genuinely having no detection lag — and it will understate true downtime every time.
Time Waiting For Parts Minutes belongs in this record because the asset genuinely wasn't running, but a plant that lets this figure dominate repeatedly has a spares-holding problem, not a maintenance-response problem. Routing that pattern to Critical Spares Review rather than absorbing it silently here is the call that keeps the two records honest.
When Line Affected is Multiple, Units Lost and Product Lost need to reflect the combined impact, not one line's figure copied across. Under-recording here because the split is awkward to calculate is the single most common way this template quietly understates cost.
Not every stoppage warrants a Failure Report ID — a changeover overrun doesn't — but an unplanned failure with a mechanical or electrical Reason Category almost always should carry one, because the downtime record times the event while the failure report investigates the cause.
What auditors find
Most common downtime record findings
The gaps that recur in downtime records tend to fall in the same six places, almost always because the record was closed for speed rather than for accuracy.
| Finding | Clause | What fixes it |
|---|---|---|
| Duration Hours is populated but every Time breakdown field is blank. | ISO 55001 cl.9.1 | Require at minimum Time To Respond and Time To Repair before a record can move to Complete, so the total can be decomposed later even if not every phase was timed live. |
| Downtime Type defaults to Unplanned regardless of what actually happened. | ISO 55001 cl.8.1 | Remove any default on Downtime Type and require an explicit choice, since a default that always fires the same way is functionally the same as not asking the question. |
| Reason Category is set but Reason Detail just restates the category. | ISO 55001 cl.9.1 | Add a minimum character check or a prompt asking what specifically failed, so Reason Detail carries information the category alone doesn't. |
| Only one of the two required signatures is present at Complete. | ISO 55001 cl.5.3 | Block the status transition to Complete until both Production and Maintenance signatures are captured, matching the joint-ownership design of the record. |
| Orders Affected is marked Significant with no Production Impact Record ID linked. | ISO 55001 cl.6.1 | Make the link field conditionally required whenever Orders Affected is Some or Significant, so the downstream impact record actually gets created. |
| Work Order ID and Failure Report ID are both left blank on unplanned events. | ISO 55001 cl.10.1 | Require at least one of the two links whenever Downtime Type is Unplanned, so the corrective loop is traceable from the downtime figure forward. |
Case in point
Case in point: the four-hour stoppage that was really three different problems
A packing line stopped for four hours and the shift log recorded one Downtime Record: Reason Category 'Mechanical failure', Duration Hours 4, Status Complete. On paper it looked like a routine repair. The phase fields, filled in only after a supervisor pushed back, told a different story: eleven minutes to notice the stop, forty minutes to get a technician on site, ninety minutes waiting for a bearing that wasn't in the local store, and only fifty minutes of actual repair.
None of those numbers pointed at maintenance competence. They pointed at a parts-holding gap and a response-time gap that a single four-hour total had completely absorbed. Once the record carried the breakdown, the ninety-minute wait routed into a Critical Spares Review instead of counting against the technician's average repair time — which is the difference between fixing the actual constraint and re-training someone for a problem they didn't cause.
The template
The template, field by field
The form exactly as it installs. Every field, option, score and conditional rule is editable, and the links to other templates come with it.
4 sections
- Reference
- MNT-011
- Archetype
- Record
- Record ID
- DT-2026-000
- Scoring
- Downtime hours
- Direction
- High is bad
- Singleton
- No
- Basis
- ISO 55001 cl.9.1
- Links
- Links Asset, Breakdown
- Tags
- Maintenance, Reliability
- Sections
- 4
- Fields
- 38
- Follow up fields
- 0
- Repeating sections
- 0
- Links out
- 5
Header
14 fieldsRecord ID*
Auto sequence. Format DT-2026-0000.
The record's own ID. Other templates point at this value.
Status*
Drives who this goes to next.
- Planned2 pts
- In progress2 pts
- Complete3 pts
- Deferred0 pts
- Open0 pts
- Closed3 pts
- Overdue0 pts
Date and Time*
Raised By*
Site*
Site ID*
Format SITE-000.
Links to FDN-001 Site ID
Area
The area within the site.
Exact Location
Drop a pin for anything hard to find.
Asset*
Asset ID*
Format AST-0000.
Links to FDN-002 Asset ID
Case ID
Copy from the record that triggered this work.
Thread key. Every record in this chain carries this value
Parent Type
What kind of record this follows.
Parent ID
The reference of that record.
Immediate predecessor record
Raised Date*
The downtime
8 fieldsDowntime Type*
Planned and unplanned downtime behave completely differently. Never combine them.
- Planned3 pts
- Unplanned0 pts
Start Time*
End Time*
Duration Hours*
Reason Category*
Reason Detail*
Work Order ID
Links to MNT-002 Work Order ID
Failure Report ID
Links to MNT-013 Case ID
Time breakdown
7 fieldsWhere The Hours Actually Go
Time to respond, time to diagnose and time to repair are separate problems with separate fixes. Recording one total hides all three.
Time To Notify Minutes
Time To Respond Minutes
Time To Diagnose Minutes
Time Waiting For Parts Minutes
Time To Repair Minutes
Time To Restart Minutes
Impact
9 fieldsLine Affected*
Units Lost
Product Lost
Orders Affected
- None3 pts
- Some1 pt
- Significant0 pts
Production Impact Record ID
Links to MNT-018 Record ID
Production*
Signature*
Maintenance*
Second Signature*
MNT-011 · record IDs look like DT-2026-000 · Links Asset, Breakdown
Open in KnowellaRun it with agents
From a document you fill in to a programme that runs itself
The form captures the event. What actually determines whether the number gets used is whether it's routed, checked and rolled up before anyone needs it for a decision.
Holds the downtime library against the asset register and work order history, flags records missing a phase breakdown or a second signature, and keeps the link to backlog and spares data live.
Picks up the production-impact fields — units lost, orders affected — and folds them into the same nonconformance view that food safety and customer complaint data already feed.
Watches for downtime events on assets already flagged as safety- or food-safety-critical, and escalates a pattern of unplanned stoppages before it becomes an incident.

Chases the missing signature or the blank phase field, rolls this period's downtime hours into one view against the trend, and holds every write for approval before it touches a record.
This template lives in KnowMaintain — asset maintenance. Work orders, planned maintenance, calibration, reliability and shutdowns.
Meet KnowMaintain→Glossary
Downtime Record definitions and key terms
- Planned downtime
- A stoppage scheduled in advance — a changeover, a clean, a planned shutdown — that is expected and does not indicate a reliability problem on its own.
- Unplanned downtime
- A stoppage caused by an unexpected failure or condition, the category that drives reliability metrics and warrants root-cause investigation.
- Time to diagnose
- The interval between a technician arriving at the asset and identifying the specific cause of the stoppage, distinct from the time spent actually repairing it.
- MTTR
- Mean time to repair — the average duration of the repair phase alone across a set of downtime events, one of the figures this record's phase breakdown makes possible to calculate.
- Ready backlog
- Outstanding work that has parts, permits and a plan already in place, as distinct from work still waiting on one of those — the concept that links a downtime event's Work Order ID forward into backlog reporting.
FAQ
Frequently asked questions about downtime record
Does every stoppage need a downtime record?+
Any stoppage long enough to matter for reporting should get one, but very short micro-stops on a line with its own stop-log are usually aggregated separately rather than raised individually here — check how your plant has drawn that line before assuming every stop qualifies.
Who signs the downtime record?+
Both a production representative and a maintenance representative sign. The record is deliberately built as a joint artefact so the duration and cause aren't disputed after the fact by either side.
What happens if the phase times don't add up to the total duration?+
Some slack is normal — phases can overlap slightly, or a small gap can go unrecorded — but a large mismatch usually means Start Time or End Time was estimated after the fact rather than logged live, and it's worth correcting before the record is signed off.
Can a downtime record exist without a linked work order?+
Yes, for planned downtime like a changeover or clean-down that never needed one. For unplanned downtime, the absence of a linked work order or failure report is usually a sign the corrective loop was never closed.
How does this differ from an OEE calculation?+
This record is the raw input, not the calculation. OEE and availability figures are built by aggregating downtime records over a period; the record itself just needs to be accurate and correctly categorised for that aggregation to mean anything.
Why is Case ID optional if the record follows an incident?+
Not every downtime event follows a prior incident, near miss or finding — many are simply mechanical failures with no upstream trigger record. Case ID is there to thread the two together when one exists, not to force a link that doesn't.
Keep going
Related templates and programmes
Industries this is written for
Programmes this belongs to
Used together in Planned Maintenance
Asset Register
Holds every piece of equipment, machine, vehicle and tool you track
Tool and Equipment Register
Holds portable tools, gauges, lifting accessories and small equipment that sit below asset level but still need control
Maintenance Request
Asks maintenance to look at a problem or carry out a job
Work Order
The main record for a planned maintenance job, covering what, where, who and when
Corrective Work Order
Covers a repair to fix something that has already failed or degraded
Emergency Work Order
Covers urgent work where equipment has stopped or become unsafe
More in Work Orders
Maintenance Request
Asks maintenance to look at a problem or carry out a job
Work Order
The main record for a planned maintenance job, covering what, where, who and when
Corrective Work Order
Covers a repair to fix something that has already failed or degraded
Emergency Work Order
Covers urgent work where equipment has stopped or become unsafe
Work Order Closeout
Confirms the job is finished, the area is safe and the equipment is fit to run
Job Plan
Sets out the steps, parts, tools, permits and time needed for a repeatable job

Written and reviewed by
Siddarth Singh
Founder & Chief Executive Officer, Knowella
Certified Safety Professional and industrial and systems engineer with more than a decade inside food supply chain, freight and manufacturing operations. This page was written against the current text of the standards it cites, not against secondary summaries of them.
- Certified Safety Professional (CSP), Board of Certified Safety Professionals
- MBA, University of Chicago Booth School of Business
- MS and BS, The Ohio State University, Industrial and Systems Engineering
- Six Sigma Black Belt
Sources and last review. Reviewed 16 August 2026 against:
- ISO 55001:2014 cl.9.1 — Monitoring, measurement, analysis and evaluation
- ISO 55001:2014 cl.8.1 — Operational planning and control
- ISO 55001:2014 cl.7.5 — Documented information
- ISO 55000:2014 — Asset management: Overview, principles and terminology
This page is general guidance, not legal advice. Confirm requirements with your jurisdiction’s regulator.