Work Order Template

A work order is the record that connects a fault to the asset that produced it. Its value is not administrative but historical: the third time a bearing fails on the same drive, the work orders either show you a pattern or they show you three unrelated repairs, and which one depends on whether anyone recorded what was actually found.

KnowMaintainRecordMNT-002Pinned in navigationFull guide
Raised by
Fault, schedule or inspection finding
Feeds
Asset history, reliability analysis, backlog

Summary

In short

  • The findings field is the entire long-term value of a work order. What was replaced is a cost record; what was found is the input to reliability analysis, and it is the field most often left blank.
  • Work orders must link to an asset that exists once. Duplicate asset records split the history, and a failure pattern spread across two identifiers is invisible to everyone.
  • Safety controls belong on the work order: the energy control procedure, permits required and any confined space or height element. Discovering the permit requirement at the machine means either a delay or a shortcut.
  • Closeout without findings, parts and actual hours makes the work order a completion notification rather than a record. It satisfies the schedule and contributes nothing to reliability.
  • PSM and mechanical integrity regimes require that deficiencies are corrected before further use or that safe operating limits are documented, which makes work order closeout a compliance event for covered equipment.
  • Emergency work orders raised after the fact are legitimate and must still be raised. Work done without a work order is work the asset history does not contain.

What it is

What it is

What is a maintenance work order?

A work order is the authorisation and record for a single piece of maintenance work on a specific asset. It captures what was requested, what was planned, what safety controls applied, what was actually done, what was found and what parts were used, and it becomes part of that asset's permanent history.

What is the difference between a work request and a work order?

A request is someone reporting that something needs attention. A work order is the planned, authorised work that follows, with a trade, a duration, parts and any permits identified. Combining them removes the planning step, which is what turns a maintenance function from planned to reactive.

When to use it

When to use it, and when not to

The work order covers a discrete piece of work on an asset. Adjacent records exist for the things it is frequently asked to do and should not.

Use it for

  • A fault, breakdown or defect requires corrective work on a specific asset
  • A planned maintenance task is due and needs executing and recording
  • An inspection or condition monitoring finding requires intervention
  • A modification is being implemented, having been approved through management of change
  • Contractor work on an asset needs authorising, controlling and recording against that asset

Not for

  • The management of change itself, which assesses and approves the modification before any work order implements it
  • Statutory examination records, which are separate documents issued by a competent person and retained per their own requirements
  • Project and capital work, which needs its own commissioning and handover rather than a maintenance record
  • The permit to work, which is a separate control document referenced by the work order rather than replaced by it
  • Purchasing and stores transactions, which the work order consumes rather than performs

Standards

What it is built against

Work orders are rarely named in regulation, but they carry the evidence that several regimes demand: that equipment is maintained, that deficiencies were corrected, and that the work was done by competent people under control.

ClauseRequirementWhere it lands
ISO 55001 cl.8.1Operational planning and control of asset management activities, with documented processesPlanning and authorisation
ISO 55001 cl.7.5Asset information requirements and control of documented informationAsset link and history
OSHA 1910.119(j)Mechanical integrity: written procedures, trained personnel, inspection and correction of deficienciesFindings and closeout
OSHA 1910.147Energy control during servicing and maintenance, machine specificSafety controls
PUWER reg.5Work equipment maintained in an efficient state, in efficient working order and in good repairExecution record
PUWER reg.6Inspection of work equipment at suitable intervals and after exceptional circumstancesInspection findings
ISO 9001 cl.7.1.3Infrastructure determined, provided and maintained for conformity of products and servicesWhole record
GFSI schemesPost-maintenance clearance and hygienic condition before production resumes in food facilitiesCloseout and handback

What it does not cover

  • Management of change, which must assess and approve a modification before a work order implements it.
  • Statutory thorough examination, which is a competent person activity with its own report and retention.
  • The permit to work, which authorises the high-risk activity and is referenced by the work order rather than contained in it.
  • Root cause analysis, which belongs in its own record where a failure is significant or repeating.
  • Spare parts master data, which the work order consumes and should not create.

Filling it in

Filling it in well

Work orders are completed under time pressure by people who want to get to the next job. The fields that matter most are the ones that feel least urgent at that moment.

Record what was found, not only what was done

The action taken is what closes the job. The condition found is what informs the next decision about that asset: whether the interval is right, whether the failure mode is what was assumed, and whether the same condition is developing elsewhere. Without it the asset history is a list of repairs with no explanation.

Attach the safety controls before the work starts

The energy control procedure, any permits required, and any confined space, height or hot work element should be identified at planning. Discovering at the machine that a permit is needed produces either a delay that nobody has time for or a shortcut that nobody records.

Capture actual hours and parts against the asset

Actual against planned is the only route to better planning, and cost against asset is the only route to a defensible repair-or-replace decision. Both are recorded at closeout by someone who has already finished the job, which is why the fields need to be quick.

Confirm handback condition, particularly in food and pharmaceutical areas

Guards refitted, tools accounted for, area cleaned, and where applicable a post-maintenance hygiene clearance before production resumes. Guards incorrectly refitted after maintenance is a recurring cause of subsequent injury, and maintenance debris is a recurring foreign body source.

Audit findings

Common audit findings

Work order findings in audits concentrate on the gap between the work being done and the record proving it.

FindingClauseWhat fixes it
Work orders closed without findings recorded, so asset history has no diagnostic content.ISO 55001 cl.7.5Make the findings field required at closeout, with free text rather than a code list alone.
Work carried out with no work order raised, particularly emergency and out-of-hours work.PUWER reg.5Permit retrospective raising within a defined window; the record matters more than the sequence.
Work order not linked to an asset, or linked to one of several duplicate asset records.ISO 55001 cl.7.5Control asset creation and merge duplicates; a split history hides the pattern.
Energy control procedure not referenced or not machine specific.1910.147(c)(4)Link the machine specific procedure to the asset so it attaches automatically.
Deficiency identified and equipment returned to service without correction or documented limits.1910.119(j)(5)Block closeout where a deficiency is open unless safe operating limits are recorded.
Actual hours and parts not captured, so planning never improves.ISO 55001 cl.8.1Capture at closeout on the device; retrospective timesheet reconstruction is not data.
Contractor work not recorded against the asset, leaving gaps in history.ISO 45001 cl.8.1.4Raise work orders for contractor work and require the findings field of them too.
Backlog not aged or prioritised by criticality, so deferral happens by omission.ISO 55001 cl.8.1Age backlog by criticality and require approval to defer above a threshold.
Post-maintenance clearance missing in food areas before production resumed.GFSI schemeAdd a hygiene clearance step to closeout for work in production areas.
Temporary repair recorded as complete, with no follow-up work order raised.1910.119(l)Flag temporary repairs and raise the permanent work order with an expiry at the same time.

Worked case

Case in point: three bearings and no pattern

A packing line drive failed in March. The work order was closed as "bearing replaced, line returned to service". It failed again in August, closed the same way by a different technician. In January it failed a third time, this time taking the shaft with it and costing two days of production.

The failure analysis found misalignment introduced during a coupling replacement eleven months before the first failure. Every technician had seen the evidence: the wear pattern was distinctive and two of them mentioned it verbally at handover. None of it reached the work order, because the field asked what was done and they answered accurately.

The information existed three times and was never recorded once. The asset history showed three bearing replacements, which reads as a consumable wearing out on schedule rather than as a system being destroyed by an alignment fault.

Definitions

Definitions and key terms

Corrective work order
Work raised in response to a fault or defect, as distinct from work raised on a schedule.
Planned maintenance work order
Work generated from a schedule against an asset, at an interval derived from failure modes or manufacturer guidance.
Backlog
Raised work not yet completed, meaningful only when aged and weighted by asset criticality.
Wrench time
The proportion of a technician's shift spent performing maintenance rather than travelling, waiting or seeking parts and permissions.
Closeout
The completion record: what was found, what was done, parts, hours and confirmation the asset is safe to return to service.
Temporary repair
A repair not meeting the design standard, which should carry an expiry and a follow-up work order rather than being closed as complete.
Criticality
The consequence of an asset failing, which should drive maintenance strategy and backlog priority rather than asset value.
Handback
Returning the asset to operations, including guard reinstatement, area clearance and, in food areas, hygiene verification.

FAQ

Frequently asked questions

Should emergency work have a work order?+

Yes, raised retrospectively if necessary. The purpose is the asset history, not the authorisation, so a work order raised after a 3am breakdown still carries the value. Requiring it before work starts in a genuine emergency produces either delay or unrecorded work, and unrecorded work is the worse outcome.

What should a work order require at closeout?+

What was found, what was done, parts consumed, actual hours, and confirmation that the asset is safe and clean to return to service. The findings field is the one that matters most and the one most often skipped, because the technician has finished the job and the question feels like paperwork.

How should backlog be managed?+

Aged and weighted by criticality rather than counted. Total backlog hours is close to meaningless: two thousand hours of low-criticality work is a resourcing question, while forty hours overdue on a critical asset is a risk. Deferral above a threshold should require approval, so that it is a decision rather than a default.

Should contractors raise work orders?+

Work done by contractors should be recorded against the asset in the same system, whether the contractor raises it or you do. Otherwise the asset history has gaps precisely where specialist work occurred, which is frequently the work most relevant to understanding a subsequent failure.

How does a work order relate to management of change?+

MOC comes first for anything that is not a like-for-like repair. Replacing a component with a different specification, altering a control setting or modifying an installation all require assessment and approval before the work order executes them. Work orders that quietly implement modifications are how undocumented change accumulates.

The agents

What the agents do with it

The work order itself is straightforward. What fails is the connective tissue: the asset it should attach to, the procedure it should carry, the deficiency it should block on, and the pattern nobody sees across three of them.

KnowMaintain

Holds work orders against the asset register, attaches the machine specific energy control procedure, and blocks closeout where a deficiency remains open.

Ella

Watches for repeating failures across work orders on the same asset or asset class, and raises the reliability question before the third occurrence.

KnowSafe

Connects permits, energy control and confined space requirements to the work order at planning rather than at the machine.

KnowQuality

Adds post-maintenance hygiene clearance in production areas, so handback is a verification rather than an assumption.

This template lives in KnowMaintainasset maintenance. Work orders, planned maintenance, calibration, reliability and shutdowns.

Meet KnowMaintain

Sources

Sources

  • ISO 55001:2014 asset management systems, clauses 7.5 and 8.1
  • 29 CFR 1910.119(j), mechanical integrity, OSHA
  • 29 CFR 1910.147, control of hazardous energy, OSHA
  • Provision and Use of Work Equipment Regulations 1998, regulations 5 and 6 (GB)
  • SAE JA1011, evaluation criteria for reliability centred maintenance processes

KnowMaintain

Also in Work Orders

6Browse the whole library
Record

Maintenance Request

Asks maintenance to look at a problem or carry out a job. Raised by anyone who spots something. Completed in under a minute with a photo and location. A work order is raised from it once maintenance accepts and plans the job.

Record

Corrective Work Order

Covers a repair to fix something that has already failed or degraded. Raised after a breakdown or a failed inspection. Completed by the technician. Links to the failure record so repair time and repeat failures can be tracked together.

Record

Emergency Work Order

Covers urgent work where equipment has stopped or become unsafe. Raised immediately, with planning done afterwards rather than before. Completed by whoever responds. High emergency work order rates are the clearest sign a maintenance programme is reactive.

Record

Work Order Closeout

Confirms the job is finished, the area is safe and the equipment is fit to run. Completed at the end of every work order. Signed by the technician and the area owner. Captures what was actually found, which is often different from what was reported.

Plan

Job Plan

Sets out the steps, parts, tools, permits and time needed for a repeatable job. Written once per job type and reused. Owned by the maintenance planner. Turns a two hour job into a one hour job by removing the hunting for parts and permits.

Record

Permit Linked Work Record

Connects maintenance work to the safety permits it requires, such as isolation, hot work or confined space. Completed alongside the work order. Signed by the technician and permit issuer. Ensures work does not start before the permit is live.

Start in Minutes, Not Weeks

Launch a Ready-Made Template and Customize It Your Way

Every template is fully editable. Adjust fields, workflows, and branding to match your processes, then deploy to your team instantly.