The recurring failure is a new machine going live with no baseline behind it: no starting vibration reading, no recorded settings, no PM plan yet written. Six months later a technician chasing a fault has nothing to compare against, and the commissioning record that was meant to fix this got signed off with the baseline fields skipped because production wanted the line running.

KnowMaintainRecordMNT-042Pinned in navigation58 fields across 5 sectionsFull researchSee the form

Reviewed by Siddarth SinghCSPLast reviewed 16 August 2026

Basis
ISO 55001 cl.8.1
Workspace
KnowMaintain
Form type
Record
Completed by
Signed by engineering, maintenance and production
Raised
At handover, before the asset enters routine service

The short version

  • A commissioning record signed off without baseline vibration, thermal or settings data leaves every later inspection with nothing valid to compare against.
  • Passing a Factory Acceptance Test does not substitute for a Site Acceptance Test; equipment that behaved correctly at the vendor's works can still fail once installed in the plant's own services and environment.
  • Handover Accepted should not be marked Yes while training, the PM plan or the criticality assessment are still outstanding, because those are the controls that keep the asset maintainable after this record closes.
  • The template holds 58 fields across 5 sections, and scores as complete or not: a partial handover with gaps is a documented risk, not a rounding error.

What this is

What is the difference between commissioning and acceptance testing?

What is the difference between commissioning and acceptance testing?

Factory Acceptance Test and Site Acceptance Test confirm the equipment performs to specification before and after installation. Commissioning is the broader handover step that follows: it confirms the tests passed, the documentation arrived, the baseline data was captured, and the asset is set up to be maintained, not just that it runs.

Why does a commissioning record need a baseline reading at all?

Condition-monitoring techniques such as vibration analysis and thermal imaging only work by comparison against a known-good state. Without a reading taken while the asset was new and correctly installed, every later inspection is compared against nothing, and early degradation looks the same as normal operation.

What does "handover accepted" actually commit the receiving team to?

Handover Accepted is production and maintenance jointly confirming they will take ownership of the asset going forward, including its warranty tracking, its PM plan and its risk assessment. A conditional acceptance should carry a documented list of what remains outstanding, not just the word "conditionally".

Scope

When is an asset commissioning record required?

This record closes out a specific asset's installation and handover. Using it to track an asset's ongoing condition, or to log a change made after it already entered service, produces a record that duplicates data other templates already own.

Use this template when

  • A new or rebuilt asset has completed installation and testing and is about to be handed to operations
  • A new record is needed; each one gets its own ID in the form COM-2026-000
  • You are running the Planned Maintenance programme and this record is the entry point onto it for a new asset
  • A linked record needs this one to exist: it links the asset register and the vendor record
  • The asset's warranty period, PM plan or criticality assessment needs a documented starting point

Do not use it for

  • Asset Criticality Assessment, which rates how important the asset is once it is in service, rather than recording the handover itself.
  • Asset Transfer Record, which covers an existing asset moving between locations, departments or sites, not its first commissioning.
  • Asset Modification Record, which covers a change made to an asset after commissioning, not the original handover.
  • Preventive Maintenance Plan, which sets out the ongoing PM schedule that this record should trigger, not duplicate.
  • Anything outside KnowMaintain, which belongs in the workspace that owns that process

Compliance mapping

Which ISO 55001 cl.8.1 requirements does this satisfy?

The clause references below map ISO 55001 clause 8.1 to the section of the form that actually carries the corresponding evidence.

ClauseRequirementWhere it lands
ISO 55001 cl.8.1Plan, implement and control the processes needed to meet asset management requirementsTesting and acceptance
ISO 55001 cl.7.6Retain documented information as evidence that processes were carried out as plannedHandover documentation
ISO 55001 cl.8.1Establish criteria for the control of the processes, and implement control in accordance with the criteriaBaseline data
ISO 55001 cl.6.1Address risks and opportunities associated with the asset before it enters serviceSetup for operation
ISO 55001 cl.7.2Determine the competence of persons who will operate and maintain the assetSetup for operation
ISO 55001 cl.4.4Include the new asset within the scope of the asset management systemSetup for operation
ISO 55001 cl.8.1Keep documented information to have confidence the processes were carried out as plannedHeader

What it does not cover

  • Baseline Settings Recorded, which allows "Partly" as an answer with no field describing which settings were actually skipped.
  • Handover Accepted, which allows "Conditionally" with no linked list of what conditions remain outstanding or who owns closing them.
  • Recommended Spares Purchased, which allows "Partly" without recording which recommended spares were left out and why.
  • Operator Training Delivered and Maintainer Training Delivered, which both allow "Partly" with no record of which named individuals were trained.
  • PM Plan Created, which can be marked Yes on the strength of a plan existing, whether or not that plan reflects the criticality assessment done on this same asset.

Global

Asset Commissioning Record requirements by country

Commissioning sits at the intersection of an asset-management standard and the machinery, food-safety and workplace-safety rules that already govern the asset being installed.

European Union

Machinery Directive 2006/42/EC and EU Regulation 2023/1230

Conformity Declaration Received and the CE-marking evidence behind it are what commissioning is meant to check before an asset is accepted into service.

Handover Accepted without a valid conformity declaration on file is accepting an asset the directive says should not yet be placed into service.

United Kingdom

PUWER 1998 reg.5 and LOLER 1998 (where lifting equipment applies)

Work equipment must be maintained in efficient working order, and that duty starts at handover; Machine Risk Assessment Done and Energy Control Procedure Written are the documented start of discharging it.

A commissioning record with those fields left No but Handover Accepted marked Yes is evidence the duty was not met from day one of service.

Food and beverage manufacturing (EHEDG/3-A)

EHEDG guidelines and 3-A Sanitary Standards

Hygienic Design Certification is optional on the form because not every asset is product-contact, but where it is, a supplier declaration is a materially weaker position than independent EHEDG or 3-A certification.

Accepting a product-contact asset on a supplier declaration alone shifts hygienic-design risk onto the buyer with no third-party verification behind it.

How to complete it

How to complete an asset commissioning record, step by step

The tick-boxes are quick to complete. The judgement calls below decide whether the resulting record is actually a usable baseline or just a signed form.

Whether the baseline was captured while it still meant something

Baseline Vibration Taken, Baseline Thermal Images Taken and Baseline Settings Recorded are only valid if taken before the asset has run long enough to develop normal wear. A baseline captured weeks into operation is not a baseline, it is a snapshot of an asset that has already started to age.

Whether a conditional handover has a real closure path

Handover Accepted marked Conditionally should never be the end state. It needs a specific list of outstanding items and an owner, otherwise "conditional" quietly becomes "permanent" the moment attention moves to the next project.

Whether the PM plan reflects the criticality just assessed

Criticality Assessed and PM Plan Created are adjacent fields for a reason: a plan written before the criticality assessment, or never revisited after it, is not actually informed by how important the asset turned out to be.

Whether training was delivered to named people, not just delivered

Operator Training Delivered and Maintainer Training Delivered marked Yes should mean specific individuals were trained and can be identified later, not that a session happened and attendance wasn't tracked.

What auditors find

Most common asset commissioning record findings

The patterns below are the ones that let a commissioning record close cleanly while leaving the plant without the baseline or controls the form exists to establish.

FindingClauseWhat fixes it
Handover Accepted is Yes while both baseline vibration and thermal fields are NoISO 55001 cl.8.1Do not permit Handover Accepted at Yes until baseline fields are resolved, or require a documented reason none was practicable.
Factory Acceptance Test Done is "Yes, not attended" and Site Acceptance Test Done is also NoISO 55001 cl.8.1Treat an unattended FAT with no SAT as unverified performance and hold handover until a site test is completed.
PM Plan Created is Yes but Criticality Assessment ID is blankISO 55001 cl.6.1Sequence the fields so criticality is assessed before the PM plan is treated as finished, and link the assessment ID.
Machine Risk Assessment Done is Yes with no Risk ID enteredISO 55001 cl.7.6Require the linked FDN-012 Risk ID whenever the risk assessment is marked complete.
Energy Control Procedure Written is "Generic only" on an asset with multiple isolation pointsISO 55001 cl.8.1Require an asset-specific procedure and Procedure ID before Handover Accepted.
Outstanding Punch List Items is greater than zero while Handover Accepted is Yes with no conditional flagISO 55001 cl.8.1Force Handover Accepted to Conditionally whenever punch list items remain open, with an owner and closure date.

Case in point

Case in point: the pump with no starting point

A dairy plant commissioned a replacement CIP pump under schedule pressure, with production pushing to restart the line. The commissioning record was signed complete: FAT attended, SAT passed, manuals received, Handover Accepted marked Yes. Baseline Vibration Taken and Baseline Settings Recorded were both left at No, with no note explaining why, because nothing in the sign-off chain required one.

Eight months later the pump began showing intermittent cavitation. The reliability engineer pulled the commissioning record expecting a baseline vibration reading to compare against and found none. Without it, there was no way to tell whether the current reading represented developing wear or had been present, and un-investigated, since day one. The plant now blocks Handover Accepted from reaching Yes while either baseline field sits at No, with an explicit override that requires the maintenance manager's second signature.

The template

The template, field by field

The form exactly as it installs. Every field, option, score and conditional rule is editable, and the links to other templates come with it.

58fields
5 sections
Reference
MNT-042
Archetype
Record
Record ID
COM-2026-000
Scoring
Complete or not
Direction
High is good
Singleton
No
Basis
ISO 55001 cl.8.1
Links
Links Asset, Vendor
Tags
Maintenance, Lifecycle
Sections
5
Fields
58
Follow up fields
3
Repeating sections
0
Links out
12
Field typesOwn ID, generated on saveCase thread and parentPick list from a registryLinked to another templateFollow up, dashed outlineScored

Header

14 fields
Text

Record ID*

Generated on save

Auto sequence. Format COM-2026-000.

The record's own ID. Other templates point at this value.

Single Choice

Status*

Scored

Drives who this goes to next.

  • Planned2 pts
  • In progress2 pts
  • Complete3 pts
  • Deferred0 pts
  • Open0 pts
  • Closed3 pts
  • Overdue0 pts
Date & Time

Date and Time*

Users

Raised By*

Pick List

Site*

From FDN-001 Site NameFilter: Status is Active
Text

Site ID*

Linked

Format SITE-000.

Links to FDN-001 Site ID

Single Choice

Area

Optional

The area within the site.

Cutting roomBoning hallPackingChill storeFreezerPasteurisingFillingCulture roomDespatchYardWorkshopPlant roomOffices
Location

Exact Location

Optional

Drop a pin for anything hard to find.

Pick List

Asset*

From FDN-002 Asset NameFilter: Site matches, Status is Active
Text

Asset ID*

Linked

Format AST-0000.

Links to FDN-002 Asset ID

Text

Project Reference

Optional
Pick List

Supplier*

From FDN-005 Vendor Name
Text

Vendor ID*

Linked

Links to FDN-005 Vendor ID

Info

The Baseline For Everything After

What you record here becomes the reference every later inspection compares against. Capture settings, readings and photographs while the equipment is new.

Handover documentation

9 fields
Single Choice

Operating Manual Received*

Scored
  • Yes3 pts
  • Partial1 pt
  • No0 pts
Single Choice

Maintenance Manual Received*

Scored
  • Yes3 pts
  • Partial1 pt
  • No0 pts
Single Choice

Drawings Received*

Scored
  • Yes3 pts
  • Partial1 pt
  • No0 pts
Single Choice

Spare Parts List Received*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Recommended Spares Purchased*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Conformity Declaration Received*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Hygienic Design Certification

OptionalScored

EHEDG or 3-A certification where product contact is involved.

  • EHEDG or 3-A4 pts
  • Supplier declaration2 pts
  • None0 pts
Single Choice

Food Grade Material Certificates

OptionalScored
  • Yes3 pts
  • Partial1 pt
  • No0 pts
Text

Manual Record ID

OptionalLinked

Links to MNT-047 Record ID

Testing and acceptance

6 fields
Single Choice

Factory Acceptance Test Done*

Scored
  • Yes, attended4 pts
  • Yes, not attended2 pts
  • No0 pts
Text

FAT Record ID

OptionalLinked

Links to MNT-068 Record ID

Single Choice

Site Acceptance Test Done*

Scored
  • Yes3 pts
  • No0 pts
Text

SAT Record ID

OptionalLinked

Links to MNT-069 Record ID

Text

Pre-Commissioning Checklist ID

OptionalLinked

Links to MNT-067 Checklist ID

Numeric Answer

Outstanding Punch List Items

OptionalScored

Baseline data

6 fields
Single Choice

Baseline Vibration Taken*

Scored
  • Yes3 pts
  • Not applicable3 pts
  • No0 pts
Single Choice

Baseline Thermal Images Taken*

Scored
  • Yes3 pts
  • Not applicable3 pts
  • No0 pts
Single Choice

Baseline Settings Recorded*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Photographs Taken*

Scored
  • Yes3 pts
  • No0 pts
File Upload

Nameplate Photograph

Optional
Numeric Answer

Initial Meter Reading

Optional

Setup for operation

23 fields
Single Choice

Added To Asset Register*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Criticality Assessed*

Scored
  • Yes3 pts
  • No0 pts
Text

Criticality Assessment ID

OptionalLinked

Links to MNT-043 Assessment ID

Single Choice

PM Plan Created*

Scored
  • Yes3 pts
  • No0 pts
Text

PM Plan ID

OptionalLinked

Links to MNT-021 Plan ID

Single Choice

Energy Control Procedure Written*

Scored
  • Yes3 pts
  • Generic only1 pt
  • No0 pts
Text

Procedure ID

OptionalLinked

Links to MNT-055 Procedure ID

Single Choice

Machine Risk Assessment Done*

Scored
  • Yes3 pts
  • No0 pts
Text

Risk ID

OptionalLinked

Links to FDN-012 Risk ID

Single Choice

Operator Training Delivered*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Maintainer Training Delivered*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Cleaning Instruction Written*

Scored
  • Yes3 pts
  • No0 pts
Numeric Answer

Warranty Period Months

Optional
Date & Time

Warranty Expiry

Optional
Single Choice

Handover Accepted*

Scored
  • Yes3 pts
  • Conditionally1 pt
  • No0 pts
Single Choice

Action Required*

Scored

Raise the action record, then enter its reference here.

  • No2 pts
  • Yes0 pts
Single Choice

Priority

OptionalScoredShows if Action Required equals Yes
  • High0 pts
  • Medium1 pt
  • Low3 pts
Text

CAPA ID

OptionalLinkedShows if Action Required equals Yes

Format CAPA-2026-00000.

Links to FDN-014 CAPA ID

Users

Action Owner

OptionalShows if Action Required equals Yes
Users

Engineering*

Signature

Signature*

Users

Production Manager*

Signature

Second Signature*

MNT-042 · record IDs look like COM-2026-000 · Links Asset, Vendor

Open in Knowella

Run it with agents

From a document you fill in to a programme that runs itself

Signing the form is the easy part. Making sure the baseline is actually captured before handover, and that the PM plan reflects the criticality just assessed, is the work that actually slips.

KnowMaintain

Holds the commissioning record against the asset register and vendor file, blocks Handover Accepted while baseline fields are outstanding, and carries the criticality link into the new PM plan.

KnowQuality

Tracks the conformity declaration and hygienic design certification as documents against the asset, and raises a CAPA automatically when a punch list item stays open past its target date.

KnowLogistics

Confirms the recommended spares from the vendor's handover pack were actually purchased and received, rather than leaving 'Partly' as an unexplained final state.

Ella
Ella

Coordinates engineering, maintenance and production sign-off, rolls outstanding baseline and training gaps into one view per asset, and holds every write for your approval before it touches a record.

This template lives in KnowMaintain — asset maintenance. Work orders, planned maintenance, calibration, reliability and shutdowns.

Meet KnowMaintain→

Glossary

Asset Commissioning Record definitions and key terms

Baseline reading
A vibration, thermal or settings measurement taken while an asset is newly installed and known to be correct, used as the reference point for every later condition check.
FAT / SAT
Factory Acceptance Test and Site Acceptance Test: pre-delivery and post-installation checks confirming equipment meets specification, run at the vendor's works and at the plant respectively.
Punch list
The list of outstanding defects or incomplete items identified during commissioning that remain to be closed before full handover.
Conformity declaration
A supplier's formal statement, often tied to CE marking, that the equipment as supplied meets the essential requirements of the applicable machinery regulations.
Energy control procedure
The documented lockout/tagout steps specific to an individual asset's isolation points, distinct from a generic site-wide LOTO policy.

FAQ

Frequently asked questions about asset commissioning record

What is the asset commissioning record template based on?+

It is built against ISO 55001 clause 8.1, which requires planned, controlled processes for bringing an asset into the management system, backed by documented evidence that those processes were actually followed.

What sections does the commissioning record contain?+

Five sections: Header, Handover documentation, Testing and acceptance, Baseline data, and Setup for operation. Together they hold 58 fields, 36 of which are required, moving from installation identity through test evidence to the controls needed for ongoing maintenance.

When should a commissioning record be raised?+

At the moment of handover, once installation and acceptance testing are complete, rather than reconstructed afterwards from memory. Each record gets an ID in the form COM-2026-000.

Why does the form ask about hygienic design certification separately from general documentation?+

Because it only applies where the asset has product contact, and a supplier declaration carries materially less assurance than independent EHEDG or 3-A certification. The form keeps that distinction visible rather than folding it into a single generic documentation tick.

What triggers the Action Required fields on this record?+

Any outstanding punch list item, missing certification, or incomplete training that the commissioning team decides needs formal follow-up. Setting it to Yes exposes Priority, CAPA ID and Action Owner.

Can the asset commissioning record template be changed?+

Yes. Every field, option, score and conditional rule is editable, and the links to the asset register and vendor record come with it. Most teams install it as it is, then tighten the baseline-data requirements once they have felt the cost of missing one.

Keep going

Related templates and programmes

Siddarth Singh

Written and reviewed by

Siddarth Singh

Founder & Chief Executive Officer, Knowella

Certified Safety Professional and industrial and systems engineer with more than a decade inside food supply chain, freight and manufacturing operations. This page was written against the current text of the standards it cites, not against secondary summaries of them.

  • Certified Safety Professional (CSP), Board of Certified Safety Professionals
  • MBA, University of Chicago Booth School of Business
  • MS and BS, The Ohio State University, Industrial and Systems Engineering
  • Six Sigma Black Belt
Verify with BCSP →

Sources and last review. Reviewed 16 August 2026 against:

  • ISO 55001:2014 cl.8.1 — Operational planning and control
  • ISO 55001:2014 cl.7.6 — Documented information
  • Machinery Directive 2006/42/EC
  • Provision and Use of Work Equipment Regulations 1998, reg.5
  • EHEDG guidelines and 3-A Sanitary Standards

This page is general guidance, not legal advice. Confirm requirements with your jurisdiction’s regulator.