Contractor Method Statement Review

A method statement review is the desk check performed before a pre-work meeting is even scheduled, and its recurring failure is politeness rather than analysis: a document written for a different site, with a different isolation point and access route, gets accepted because rejecting it delays a contractor already booked in. The review exists to catch that document before the crew is on site.

KnowContractorReviewCON-012Pinned in navigation52 fields across 6 sectionsFull researchSee the form

Reviewed by Siddarth SinghCSPLast reviewed 16 August 2026

Basis
ISO 45001 cl.8.1.4
Workspace
KnowContractor
Form type
Review
Completed by
Contract owner with safety, before work starts
Feeds
Pre-work meeting, permits, briefing

The short version

  • A method statement review is a gate, not a formality. It exists to stop work starting on a document that does not describe the actual job, and accepting a generic document defeats that purpose entirely.
  • Site-specific means naming this equipment, these hazards and these controls, in the order the work will actually happen. A document that could apply to any site on any day has told the reviewer nothing.
  • The hierarchy of controls applies here as it does in a risk assessment. A method statement concluding in PPE and training without explaining why higher controls were rejected has not engaged with its own hazards.
  • A control the contractor cannot actually deploy on this site is not a control. Equipment they will not bring, permits not yet arranged, or isolations the site cannot support belong to the reviewer, not to hope.
  • Acceptance is not the end state. The document has to reach the crew doing the work and be present at the work point, or the review has protected a filing cabinet rather than a job.

What this is

What is a contractor method statement review?

What is a contractor method statement review?

A structured check of a contractor's proposed method of work and its risk assessment, carried out before work begins. It asks whether the document is specific to this site and task, whether the hazards named match what is actually present, and whether the proposed controls are things the contractor can and will do.

Who should carry out the review?

The contract owner, working with safety, and specifically someone with enough knowledge of the trade to tell a real sequence of work from a rewritten template. A reviewer who does not understand the task cannot judge whether the sequence is genuinely site-specific or merely names the site.

What happens if the method statement is rejected?

Work does not start. The reviewer records what is wrong, the contractor submits a revised version, and the revision is checked before mobilisation proceeds. A document accepted with unresolved concessions should be a visible decision, not a silent lowering of the bar.

Scope

When is a contractor method statement review required?

This review sits between the contractor's paperwork and the pre-work meeting held on site. Confusing the two produces a record that looks thorough but has skipped the step that stops bad work.

Use this template when

  • A contractor submits a method statement and risk assessment for a work package before it is due to start
  • An existing method statement is reused for a similar task and needs re-checking against this site
  • A method statement has come back from the contractor after an earlier rejection and needs re-review
  • A high-risk task is planned and the written method is the primary control on how it is done
  • A permit-to-work or isolation depends on a method statement that has not yet been checked

Do not use it for

  • Pre-Work Meeting Record, the face-to-face briefing held with the crew immediately before mobilising, once this review has already accepted the document
  • Contractor Site Induction, which covers general site rules and hazards rather than the specific task method
  • Contractor Competency Verification, which checks an individual worker's tickets and training, not adequacy of the method
  • The underlying risk assessment itself, the contractor's document, referenced here, not reproduced
  • A permit to work, the point-in-time authorisation issued once the method statement is accepted, not the review that accepts it

Compliance mapping

Which ISO 45001 cl.8.1.4 requirements does this satisfy?

ISO 45001 treats contracted work as something the organisation must actively coordinate, not something a contractor's paperwork automatically satisfies. The review is where that duty becomes a dated decision.

ClauseRequirementWhere it lands
ISO 45001 cl.8.1.4.2Hazards arising from contracted work must be identified and the associated risks assessed and controlled, coordinated with the organisation's own arrangementsHazards and controls
ISO 45001 cl.8.1.1Operational processes must have established criteria, with control implemented against those criteria, including the sequence and conditions of workQuality of the document
ISO 45001 cl.8.1.4.2Contractor activities and materials with the potential to affect the organisation's workers must be identified before work proceedsHazards and controls
ISO 45001 cl.7.2Competence of persons doing work affecting OH&S performance must be determined, evidenced and verifiedResources and competence
ISO 45001 cl.6.1.2.2Risk assessment methodology and criteria must be defined and consistently applied, and can be compared against the organisation's own assessment of the same workRelated records
ISO 45001 cl.8.2Emergency preparedness and response arrangements for foreseeable emergencies must be established and understood by those affectedHazards and controls
ISO 45001 cl.9.1.1The organisation must monitor and evaluate the extent to which requirements are being fulfilledOutcome

What it does not cover

  • Pre-Work Meeting Record, the face-to-face briefing held with the crew immediately before mobilising, once this review has accepted the document.
  • The underlying risk assessment itself, the contractor's own record, referenced here for comparison, not reproduced or re-authored.
  • Contractor Site Induction, which covers site-wide rules, emergency arrangements and permit requirements, not the task method.
  • Contractor Competency Verification, which verifies named individuals hold the tickets and training required, not adequacy of the method.
  • Permit to work, the time-bound authorisation issued once the method statement is accepted, not the review that accepts it.

Global

Contractor Method Statement Review requirements by country

No jurisdiction prescribes a method statement review by that name. The duty comes from the general obligation to control contracted-out work, which this review turns into a recorded decision.

United States

OSHA General Duty Clause; multi-employer worksite doctrine

No standard names a method statement, but OSHA can cite a host employer who knew of a contractor's unsafe method and did not act.

An accepted document naming inadequate controls is evidence the host had the chance to catch the hazard and did not.

United Kingdom

MHSWR 1999, reg.11-12; CDM 2015 for construction work

Duties to cooperate and coordinate where more than one employer shares a workplace, with CDM setting construction-specific duties.

A generic document accepted unchallenged undermines the client's and principal contractor's own cooperation duties.

International

ISO 45001 cl.8.1.4.2

Management system requirement to coordinate hazard identification and risk control with contractors before work affects the workforce.

Auditors look for evidence the review happened and actually rejected inadequate documents, not just that a file exists.

How to complete it

How to complete a contractor method statement review, step by step

The template checks whether each element of the document is present. It does not ask the four questions that decide whether the acceptance was a real decision.

Reject generic documents rather than editing them

A reviewer who quietly fixes a method statement to make it pass has removed the evidence it was generic, and taken on authorship of a document they cannot verify on site. The right response to a generic submission is rejection with named gaps, not correction.

Rate the document as submitted, not as it will probably be revised

Site specific and names the actual equipment ask about the document in front of the reviewer. Scoring against an assumed future revision converts the review into a formality if that revision never arrives as promised.

Test whether the controls are practical with what this contractor will actually bring

A control requiring equipment not costed in, a permit nobody has started, or an isolation the site cannot support by the planned start is not a control, it is a sentence. The reviewer's job is to ask what is actually turning up.

Close the loop to the crew, not just to the file

Briefed to the crew and copy available at the work point decide whether the review protected anyone. A document that never reaches the people doing the job has produced a compliant record and an unprotected task.

What auditors find

Most common contractor method statement review findings

Method statement review findings rarely concern whether the review happened. They concern whether accepting the document was the right call, and whether anyone downstream ever saw the result.

FindingClauseWhat fixes it
Generic method statement accepted despite not naming this site's equipment, access route or isolation points.ISO 45001 cl.8.1.4.2Score site specific honestly; reject and return with the gaps named.
Hazards and controls section concludes in PPE and supervision without the hierarchy of controls being addressed.ISO 45001 cl.8.1.1Require a stated reason why elimination, substitution and engineering control were rejected first.
Method statement accepted with concession, but the changes required were never verified in a revised version.ISO 45001 cl.9.1.1Do not close the review as accepted until the revision is received and checked against the named gaps.
Document accepted but never linked to a pre-work meeting or briefed to the crew before mobilisation.ISO 45001 cl.7.4Hold the record open until briefed to the crew and copy available at the work point are confirmed.
Isolation sequence or emergency and rescue arrangements marked not applicable without a stated reason.ISO 45001 cl.8.2Require a reason wherever not applicable is selected, so the judgement is visible, not assumed.
Review carried out by someone without competence in the trade being reviewed.ISO 45001 cl.7.2Route specialist trades to a reviewer competent in that trade, not the contract owner alone.

Case in point

Case in point: the review that accepted the wrong revision

A refrigeration contractor submitted a method statement for a compressor changeout that named a different plant room layout, a leftover from a previous job at a sister site. The reviewer flagged it as generic, marked accepted with concession, and listed the changes required: correct isolation points, this site's confined space arrangements, and the actual lifting route through the loading bay.

The contractor sent a revised document two days later. It was filed and marked revised version received, but nobody re-checked it against the changes requested, and the review was never reopened. The revision still described the wrong isolation sequence, caught only by the contractor's own supervisor during the pre-work meeting, not by the review meant to have already settled it.

The template

The template, field by field

The form exactly as it installs. Every field, option, score and conditional rule is editable, and the links to other templates come with it.

52fields
6 sections
Reference
CON-012
Archetype
Review
Record ID
CMSR-2026-000
Scoring
Adequacy score
Direction
High is good
Singleton
No
Basis
ISO 45001 cl.8.1.4
Links
Links Vendor, Job, Risk Assessment
Tags
Contractor, Assurance
Sections
6
Fields
52
Follow up fields
3
Repeating sections
0
Links out
4
Field typesOwn ID, generated on saveCase thread and parentPick list from a registryLinked to another templateFollow up, dashed outlineScored

Header

12 fields
Text

Review ID*

Generated on save

Auto sequence. Format MSR-2026-000.

The record's own ID. Other templates point at this value.

Single Choice

Status*

Scored

Drives who this goes to next.

  • Planned2 pts
  • In progress2 pts
  • Complete3 pts
  • Deferred0 pts
  • Open0 pts
  • Closed3 pts
  • Overdue0 pts
Date & Time

Date and Time*

Users

Completed By*

Pick List

Site*

From FDN-001 Site NameFilter: Status is Active
Text

Site ID*

Linked

Format SITE-000.

Links to FDN-001 Site ID

Pick List

Contractor*

From FDN-005 Vendor NameFilter: Status is Approved
Text

Vendor ID*

Linked

Format VEN-0000.

Links to FDN-005 Vendor ID

Info

Reject Generic Documents

A method statement that could apply to any job on any site adds nothing. It must name this equipment, these hazards and these controls, in the order the work will happen.

Text

Work Package*

Text

Document Reference

Optional
Users

Reviewer*

Quality of the document

6 fields
Single Choice

Site Specific*

Scored
  • Yes3 pts
  • Partly1 pt
  • Generic0 pts
Single Choice

Names The Actual Equipment*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Sequence Of Work Clear*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Written In Plain Language*

Scored

The people doing the work have to be able to read and follow it.

  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Usable By The Crew On Site*

Scored
  • Yes3 pts
  • Marginal1 pt
  • No0 pts
Single Choice

Length Reasonable*

Scored
  • Yes3 pts
  • Too long1 pt
  • Too brief0 pts

Hazards and controls

9 fields
Single Choice

All Significant Hazards Identified*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Our Site Hazards Included*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Controls Follow The Hierarchy*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Controls Practical On Our Site*

Scored

A control requiring equipment they will not bring is not a control.

  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Permits Identified*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Isolation Sequence Described*

Scored
  • Yes3 pts
  • Not applicable3 pts
  • No0 pts
Single Choice

Emergency And Rescue Arrangements*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Food Safety Controls Included*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Waste And Clean Up Described*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts

Resources and competence

5 fields
Single Choice

People And Roles Named*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Competencies Stated*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Equipment Listed*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Supervision Arrangements Stated*

Scored
  • Yes3 pts
  • Vague1 pt
  • No0 pts
Single Choice

Inspection And Test Points Included

OptionalScored
  • Yes3 pts
  • No1 pt

Related records

1 field
Text

Risk ID

OptionalLinked

Our assessment of the same work, for comparison.

Links to FDN-012 Risk ID

Outcome

19 fields
Numeric Answer

Items Assessed*

Excludes anything marked N/A.

Numeric Answer

Items Failed*

Numeric Answer

Score Percent*

Scored

Calculated on submission. High is good. N/A items leave the denominator.

Single Choice

Result Band*

Scored
  • Pass3 pts
  • Caution1 pt
  • Fail0 pts
Numeric Answer

Completeness Percent*

How much of the template was actually answered. A high score on a half completed form is not a high score.

Single Choice

Accepted*

Scored
  • Yes3 pts
  • Accepted with concession1 pt
  • Rejected0 pts
Text

Changes Required

Optional
Single Choice

Revised Version Received

Optional
YesNot neededNo
Single Choice

Briefed To The Crew*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Copy Available At The Work Point*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Deviation Process Explained*

Scored

If conditions differ from the method statement, they stop and re-agree. They do not improvise.

  • Yes3 pts
  • No0 pts
Single Choice

Action Required*

Scored

Raise the action record, then enter its reference here.

  • No2 pts
  • Yes0 pts
Single Choice

Priority

OptionalScoredShows if Action Required equals Yes
  • High0 pts
  • Medium1 pt
  • Low3 pts
Text

CAPA ID

OptionalLinkedShows if Action Required equals Yes

Format CAPA-2026-00000.

Links to FDN-014 CAPA ID

Users

Action Owner

OptionalShows if Action Required equals Yes
Users

Reviewer*

Signature

Signature*

Users

Contractor Supervisor*

Signature

Second Signature*

CON-012 · record IDs look like CMSR-2026-000 · Links Vendor, Job, Risk Assessment

Open in Knowella

Run it with agents

From a document you fill in to a programme that runs itself

The review itself is a judgement call made once. What fails afterwards is the handoff: the accepted document that never reaches the crew, and the revision that was received but never re-checked.

KnowContractor

Holds the review against the job and vendor record, and blocks mobilisation steps until an accepted or revised document is on file.

KnowSafe

Checks the hazards and controls named in the method statement against the site's own hazard register, and flags where they diverge.

KnowTrain

Connects competencies stated in the method statement to individual verification records for the crew actually turning up.

Ella
Ella

Watches for a review accepted with concession that never shows a revised version received, and raises it before the pre-work meeting.

This template lives in KnowContractor — contractor management. Prequalification, approval, induction, permits and performance.

Meet KnowContractor→

Glossary

Contractor Method Statement Review definitions and key terms

Method statement
The contractor's written description of how a task will be carried out, in sequence, including the plant, people and controls involved.
Site specific
A method statement naming the actual site, equipment, hazards and access arrangements rather than a generic version reused across jobs.
Hierarchy of controls
The ranked sequence of control types: elimination, substitution, engineering controls, administrative controls, then personal protective equipment.
Accepted with concession
A review outcome where the document is approved despite a named shortfall, rather than rejected outright, with the shortfall recorded rather than absorbed.
Deviation process
The agreed procedure if site conditions do not match the method statement: the crew stops and re-agrees the method rather than improvising.

FAQ

Frequently asked questions about contractor method statement review

How is this different from a pre-work meeting?+

The review is a desk check of a written document, carried out before mobilisation, and can result in rejection. The pre-work meeting is a face-to-face briefing held once the document has been accepted, walking through what was reviewed rather than reassessing it.

Can we accept a method statement with known gaps?+

Yes, but as a visible decision. Accepted with concession, with changes required recorded, keeps the gap on record and forces a decision about closing it, rather than losing it in a plain acceptance.

Who is competent to review a method statement?+

Someone who understands the trade well enough to tell a genuine sequence from a document that has simply had the site name changed. A safety generalist can check sections are present; only someone who knows the task can check the content is real.

Does the review replace the contractor's own risk assessment?+

No. The risk assessment remains the contractor's document. The review checks it against the organisation's own assessment of the same work where one exists, and records whether it is adequate, but does not become that assessment.

What if the contractor cannot revise the document in time?+

The work does not start. The review exists to be a gate a booked schedule does not override; treating the deadline as more urgent than the gap defeats the point of doing it at all.

Should the review be repeated for a routine, repeated task?+

Re-check whenever the site, scope or method changes, even for a contractor whose work is normally routine. Adequate for one site or date is not automatically adequate for the next.

Keep going

Related templates and programmes

Industries this is written for

Siddarth Singh

Written and reviewed by

Siddarth Singh

Founder & Chief Executive Officer, Knowella

Certified Safety Professional and industrial and systems engineer with more than a decade inside food supply chain, freight and manufacturing operations. This page was written against the current text of the standards it cites, not against secondary summaries of them.

  • Certified Safety Professional (CSP), Board of Certified Safety Professionals
  • MBA, University of Chicago Booth School of Business
  • MS and BS, The Ohio State University, Industrial and Systems Engineering
  • Six Sigma Black Belt
Verify with BCSP →

Sources and last review. Reviewed 16 August 2026 against:

  • ISO 45001:2018 clauses 8.1.4, 8.1.1, 7.2 and 6.1.2
  • Management of Health and Safety at Work Regulations 1999, regulations 11-12 (GB)
  • Construction (Design and Management) Regulations 2015 (GB)
  • OSH Act Section 5(a)(1) and multi-employer worksite doctrine (US)

This page is general guidance, not legal advice. Confirm requirements with your jurisdiction’s regulator.