Factory Acceptance Test Record

The recurring failure at FAT is testing convenience rather than reality: a filler run on water instead of the viscous product it will actually handle, a changeover demonstrated once rather than under a full shift, guarding checked by eye rather than by function. Every shortcut passes on the day and reappears later as a site acceptance failure, a commissioning delay, or a warranty dispute once the invoice is already paid.

KnowMaintainRecordMNT-06851 fields across 5 sectionsFull researchSee the form

Reviewed by Siddarth SinghCSPLast reviewed 16 August 2026

Basis
ISO 55001 cl.8.3
Workspace
KnowMaintain
Form type
Record
Completed by
Witnessed by your engineering team at the supplier's works
Accepted for shipment
Yes, with punch list, or No — drives whether it ships

The short version

  • A Factory Acceptance Test Record only proves what it actually tests — a pass on water tells you the pump seals, not that it will move your product at the viscosity and rate you need.
  • Attendance by your own engineer, in person or as a remote witness, is what turns a supplier's internal test into evidence you can rely on; a report emailed after the fact is not the same thing.
  • Acceptance with a punch list is a conditional pass, not a pass — the punch list items must close before the equipment reaches site, or they become the site team's problem to discover.
  • The record exists to feed the next one: without a Record ID here, the Site Acceptance Test Record and later commissioning steps have nothing to reference.

What this is

What is a Factory Acceptance Test Record?

What is a Factory Acceptance Test Record?

A Factory Acceptance Test Record is the evidence that new equipment met its acceptance criteria at the supplier's works before it left the building. It covers functional tests, rated output, cleaning and changeover, and the safety and documentation the supplier owes you. It is signed by both your engineer and the supplier's representative before the equipment ships.

How is a FAT different from a SAT?

A Factory Acceptance Test happens at the supplier's premises, before the equipment ships, and proves the machine as built. A Site Acceptance Test happens after installation at your site, with your services connected and your product running, and proves the machine as installed. A clean FAT with an open punch list still needs a SAT to confirm the punch list was actually closed.

Who needs to attend a Factory Acceptance Test?

At minimum, an engineer from your side witnessing in person or remotely, and a representative from the supplier running the equipment. Where a quality or food safety requirement applies, whoever owns cleaning validation should also see the strip-down and clean before it is accepted, not just take the supplier's word for it.

Scope

When is a factory acceptance test record required?

This record proves the equipment before it leaves the supplier's building. Using it to test installation, or to record commissioning decisions, blurs work that belongs to the templates either side of it.

Use this template when

  • New equipment or a modified line has been built and is ready to test before shipment
  • A new record is needed; each one gets its own ID in the form FAT-2026-000
  • You are running the Capital Projects and Commissioning programme and this is the pre-shipment step
  • The equipment specification (MNT-091) sets the acceptance criteria this test will check against
  • A linked record needs this one to exist: links Asset, Vendor

Do not use it for

  • Pre-Commissioning Checklist, which confirms a new installation is complete and safe before it is energised or run on your site.
  • Site Acceptance Test Record, which records testing of new equipment once installed at your site.
  • Equipment Specification Record, which defines the acceptance criteria this test checks, rather than the test result itself.
  • Installation Progress Record, which tracks the physical build on site, not the pre-shipment test at the supplier.
  • Anything outside KnowMaintain, which belongs in the workspace that owns that process

Compliance mapping

Which ISO 55001 cl.8.3 requirements does this satisfy?

ISO 55001 cl.8.3 expects new or modified assets to be verified against their acceptance criteria before they are relied upon. The clause map below shows where that expectation lands in the form.

ClauseRequirementWhere it lands
ISO 55001 cl.8.3The asset's identity, site and vendor are established before testing beginsHeader
ISO 55001 cl.8.3Attendance and an agreed test protocol are confirmed before the test runs, not reconstructed afterwardsHeader
ISO 55001 cl.8.3Each test is checked against a stated acceptance criterion and a pass or fail recordedTests
ISO 55001 cl.8.3Output, product representativeness and operating conditions are verified, not assumedPerformance verification
ISO 55001 cl.8.3Guarding, safety functions and conformity documentation are confirmed before the asset is acceptedSafety and documentation
ISO 55001 cl.8.3Manuals, spares and software are confirmed present so the asset can be maintained once it arrivesSafety and documentation
ISO 55001 cl.8.3A scored outcome and an explicit shipment decision close the recordOutcome

What it does not cover

  • Tested With Our Product Or Simulant, which recorded a pass on water rather than the product the equipment will actually run.
  • Test Protocol Agreed In Advance, which was answered No, meaning the acceptance criteria were negotiated on the day rather than fixed beforehand.
  • Witnessed By Us, which was answered No for a test result later disputed by the site team.
  • Accepted For Shipment, which was marked Yes over an open punch list with no closure date attached.
  • Conformity Declaration Available, which was left No with the equipment already released to ship.

Global

Factory Acceptance Test Record requirements by country

A Factory Acceptance Test sits under whichever machinery safety regime governs the country the equipment is bought into, not the country it is built in.

European Union

Machinery Regulation (EU) 2023/1230, replacing Directive 2006/42/EC

Requires a Declaration of Conformity and CE marking before machinery is placed on the market, covering guarding, safety functions and the technical file.

The Conformity Declaration Available and Guarding As Specified fields are where that evidence is checked before the equipment ships, not assumed from the supplier's brochure.

United Kingdom

Supply of Machinery (Safety) Regulations 2008, UKCA marking

Mirrors the EU regime for the UK market: a UK Declaration of Conformity and UKCA mark are required before relevant machinery is supplied.

Where equipment is sourced from an EU supplier for a UK site, confirm which mark and declaration actually apply — CE alone does not satisfy a UK-market requirement.

United States

OSHA 29 CFR 1910 Subpart O, machine guarding, and the General Duty Clause

Sets no federal requirement for a factory acceptance test itself, but does require guards and safety functions to be in place before a machine is put into service.

The FAT is the practical mechanism for proving that OSHA-relevant guarding and safety functions exist before the equipment ever reaches the plant floor.

How to complete it

How to complete a factory acceptance test record, step by step

A record with every field answered Yes is not the same as a record that will hold up when something goes wrong on site. These are the calls that decide whether it does.

Whether a punch list voids the acceptance

Accepted For Shipment allows 'With punch list' as a valid outcome, but that only holds if every open item has an owner and a closure date attached before the equipment leaves. A punch list with no plan to close it is a deferred fail, whatever the field says.

Whether remote witnessing was good enough

Attended By Us scores a remote witness lower than attendance in person for a reason. A video link catches the test running; it does not catch someone rerunning it off-camera after a failure. Reserve remote witnessing for lower-risk equipment, not for anything with a food safety or guarding stake.

Whether the product used to test actually represents your process

A representative simulant can be a legitimate substitute for your real product where the real product is hazardous or unavailable, but the case for calling it 'representative' should be recorded, not assumed. If nobody can say why the simulant behaves like the product, treat the result as a water test.

Whether documentation gaps get chased before or after shipment

Manuals, spares lists and conformity declarations are cheap to obtain before the equipment ships and expensive to obtain after it is running in production. Marking them 'No' and accepting anyway defers a cost onto whoever holds the maintenance plan, usually without telling them.

What auditors find

Most common factory acceptance test record findings

Patterns that show up across FAT records once you compare enough of them.

FindingClauseWhat fixes it
Performance is verified on water or air, not on the product or a genuine simulantISO 55001 cl.8.3Require Tested With Our Product Or Simulant to score at the 'our product' or 'representative simulant' level before the test counts as run, and hold shipment on anything scored 'water only' for equipment where product behaviour is the whole point.
Test protocol agreed after the equipment already failed a first attemptISO 55001 cl.8.3Make Test Protocol Agreed In Advance a gate on scheduling the FAT date, not a box ticked retrospectively once the supplier is ready.
Cleaning is watched being started but not watched being finishedISO 55001 cl.8.3Score Cleaning Demonstrated only where the strip-down and reassembly were both witnessed; a partial cleaning demonstration should score as Partly, not Yes.
Punch list items ship with the equipment and arrive with no dates attachedISO 55001 cl.8.3Require Conditions Of Acceptance to name a closure date for every punch list item before Accepted For Shipment can be marked 'With punch list'.
Software and backups are marked Not Applicable by default rather than checkedISO 55001 cl.8.3Treat Not Applicable on Software And Backups Provided as a claim that needs a reason on file, not a default for anything with a control panel.
Second signature is collected after the equipment has already left the buildingISO 55001 cl.8.3Sequence the record so both signatures are required before Status can move to Complete, not after shipment has already happened.

Case in point

Case in point: the filler that passed on water

A filler for a viscous dairy product was tested at the supplier's works and passed every functional check — output, changeover, cleaning — all run on water because the real product wasn't available on site. Tested With Our Product Or Simulant was scored 'Water only', and Accepted For Shipment was marked Yes anyway because every other test had passed.

Three weeks after installation, the filler's rated output on the real product came in at sixty per cent of the FAT figure, and cleaning took twice as long because the higher-viscosity product fouled parts the water test never touched. The fix cost a site visit, a nozzle change and a week of lost changeover time — all of it avoidable if the FAT score had held the line it was designed to hold.

The template

The template, field by field

The form exactly as it installs. Every field, option, score and conditional rule is editable, and the links to other templates come with it.

51fields
5 sections
Reference
MNT-068
Archetype
Record
Record ID
FAT-2026-000
Scoring
Pass or fail
Direction
High is good
Singleton
No
Basis
ISO 55001 cl.8.3
Links
Links Asset, Vendor
Tags
Commissioning, Supplier
Sections
5
Fields
51
Follow up fields
3
Repeating sections
1
Links out
4
Field typesOwn ID, generated on saveCase thread and parentPick list from a registryLinked to another templateFollow up, dashed outlineScored

Header

17 fields
Text

Record ID*

Generated on save

Auto sequence. Format FAT-2026-000.

The record's own ID. Other templates point at this value.

Single Choice

Status*

Scored

Drives who this goes to next.

  • Planned2 pts
  • In progress2 pts
  • Complete3 pts
  • Deferred0 pts
  • Open0 pts
  • Closed3 pts
  • Overdue0 pts
Date & Time

Date and Time*

Users

Raised By*

Pick List

Site*

From FDN-001 Site NameFilter: Status is Active
Text

Site ID*

Linked

Format SITE-000.

Links to FDN-001 Site ID

Single Choice

Area

Optional

The area within the site.

Cutting roomBoning hallPackingChill storeFreezerPasteurisingFillingCulture roomDespatchYardWorkshopPlant roomOffices
Location

Exact Location

Optional

Drop a pin for anything hard to find.

Pick List

Asset*

From FDN-002 Asset NameFilter: Site matches, Status is Active
Text

Asset ID*

Linked

Format AST-0000.

Links to FDN-002 Asset ID

Pick List

Supplier*

From FDN-005 Vendor Name
Text

Vendor ID*

Linked

Links to FDN-005 Vendor ID

Text

Test Location*

Info

Cheapest Place To Find Problems

A fault found at the supplier's works costs a fraction of the same fault found on your floor after installation. Send people and give them time.

Single Choice

Attended By Us*

Scored
  • Yes3 pts
  • Remote witness2 pts
  • No0 pts
Text

Our Attendees

Optional
Single Choice

Test Protocol Agreed In Advance*

Scored
  • Yes3 pts
  • No0 pts

Tests

Repeats6 fields
Text

Test Description*

Text

Acceptance Criteria*

Text

Result*

Single Choice

Passed*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Witnessed By Us*

Scored
  • Yes3 pts
  • No0 pts
File Upload

Evidence

Optional

Performance verification

6 fields
Single Choice

Rated Output Achieved*

Scored
  • Yes3 pts
  • Marginal1 pt
  • No0 pts
Single Choice

Tested With Our Product Or Simulant*

Scored

Machines tested on water and delivered for viscous dairy product are a familiar disappointment.

  • Our product4 pts
  • Representative simulant3 pts
  • Water only0 pts
Single Choice

Tested At Our Operating Conditions*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Changeover Time Demonstrated

OptionalScored
  • Yes3 pts
  • No0 pts
Single Choice

Cleaning Demonstrated*

Scored

Watch it being stripped and cleaned before you accept it.

  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Cleaning Time Acceptable

OptionalScored
  • Yes3 pts
  • Marginal1 pt
  • No0 pts

Safety and documentation

6 fields
Single Choice

Guarding As Specified*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Safety Functions Demonstrated*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Conformity Declaration Available*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Manuals Available*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Spare Parts List Provided*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Software And Backups Provided

OptionalScored
  • Yes3 pts
  • Not applicable3 pts
  • No0 pts

Outcome

16 fields
Numeric Answer

Items Assessed*

Excludes anything marked N/A.

Numeric Answer

Items Failed*

Numeric Answer

Score Percent*

Scored

Calculated on submission. High is good. N/A items leave the denominator.

Single Choice

Result Band*

Scored
  • Pass3 pts
  • Caution1 pt
  • Fail0 pts
Numeric Answer

Completeness Percent*

How much of the template was actually answered. A high score on a half completed form is not a high score.

Numeric Answer

Punch List Items*

Scored
Single Choice

Accepted For Shipment*

Scored
  • Yes3 pts
  • With punch list1 pt
  • No0 pts
Text

Conditions Of Acceptance

Optional
Single Choice

Action Required*

Scored

Raise the action record, then enter its reference here.

  • No2 pts
  • Yes0 pts
Single Choice

Priority

OptionalScoredShows if Action Required equals Yes
  • High0 pts
  • Medium1 pt
  • Low3 pts
Text

CAPA ID

OptionalLinkedShows if Action Required equals Yes

Format CAPA-2026-00000.

Links to FDN-014 CAPA ID

Users

Action Owner

OptionalShows if Action Required equals Yes
Users

Engineering*

Signature

Signature*

Users

Supplier Representative*

Signature

Second Signature*

MNT-068 · record IDs look like FAT-2026-000 · Links Asset, Vendor

Open in Knowella

Run it with agents

From a document you fill in to a programme that runs itself

The form is the easy part. Keeping FAT records tied to the right asset and vendor, and chasing punch list closure before shipment, is the work that actually slips.

KnowMaintain

Holds the Factory Acceptance Test Record against the asset and vendor it belongs to, and won't let Accepted For Shipment go through with an open punch list nobody owns.

KnowSafe

Tracks guarding, safety function and conformity declaration evidence gathered at FAT so it carries forward into the asset's safety file rather than getting left at the supplier's works.

KnowQuality

Picks up the cleaning and product-representativeness scores from FAT and flags where a pass was earned on water or a simulant rather than the real product.

Ella
Ella

Chases outstanding attendee sign-offs and punch list items across every open FAT, and holds every write for your approval before it touches a record.

This template lives in KnowMaintain — asset maintenance. Work orders, planned maintenance, calibration, reliability and shutdowns.

Meet KnowMaintain→

Glossary

Factory Acceptance Test Record definitions and key terms

FAT
Factory Acceptance Test. Testing carried out at the supplier's premises before equipment ships, proving the machine as built.
SAT
Site Acceptance Test. Testing carried out after installation at your site, proving the machine as installed and running your product.
Punch list
The list of open items found during a test that remain to be fixed before final acceptance is unconditional.
Conformity declaration
The supplier's formal statement, tied to CE or UKCA marking, that the equipment meets the applicable machinery safety requirements.
Representative simulant
A substitute substance used in testing that is chosen to behave like the real product on the properties the test actually depends on, such as viscosity or fouling.

FAQ

Frequently asked questions about factory acceptance test record

What is the Factory Acceptance Test Record template based on?+

It is built against ISO 55001 cl.8.3, which covers the operation of assets including verifying them against acceptance criteria before they are relied upon. ISO 55001 is the international standard for getting value from physical assets across their whole life, and it underpins the maintenance templates in this library.

What sections does the Factory Acceptance Test Record contain?+

There are five sections: Header, Tests, Performance verification, Safety and documentation, and Outcome. Together they hold 51 fields, 39 of which are required.

How often is a Factory Acceptance Test Record raised?+

A new record is raised whenever new or modified equipment is ready to test at the supplier's works, before it ships. Each one is given an ID in the form FAT-2026-000, so it can be traced from the Site Acceptance Test Record and later commissioning steps.

Which programme does the Factory Acceptance Test Record belong to?+

It is part of Capital Projects and Commissioning, the programme that carries equipment from specification through to a post-project review, so it arrives with its procedures, training and spares rather than after them.

How is a Factory Acceptance Test Record scored?+

Scoring is pass or fail, with high scores good throughout. Fields like Tested With Our Product Or Simulant and Cleaning Demonstrated carry more weight than a bare Yes or No, because they distinguish a test that proves something from one that only looks complete.

Can the Factory Acceptance Test Record template be changed?+

Yes. Every field, option, score and conditional rule is editable, and the links to the Asset and Vendor records come with it. Most teams install it as it is, run it through one project, then adjust the acceptance criteria fields to match how they actually buy equipment.

Keep going

Related templates and programmes

Siddarth Singh

Written and reviewed by

Siddarth Singh

Founder & Chief Executive Officer, Knowella

Certified Safety Professional and industrial and systems engineer with more than a decade inside food supply chain, freight and manufacturing operations. This page was written against the current text of the standards it cites, not against secondary summaries of them.

  • Certified Safety Professional (CSP), Board of Certified Safety Professionals
  • MBA, University of Chicago Booth School of Business
  • MS and BS, The Ohio State University, Industrial and Systems Engineering
  • Six Sigma Black Belt
Verify with BCSP →

Sources and last review. Reviewed 16 August 2026 against:

  • ISO 55001:2014 cl.8.3 — Asset management systems, Operation
  • Machinery Regulation (EU) 2023/1230 — Declaration of Conformity and CE marking
  • Supply of Machinery (Safety) Regulations 2008 — UKCA marking
  • OSHA 29 CFR 1910 Subpart O — Machine guarding

This page is general guidance, not legal advice. Confirm requirements with your jurisdiction’s regulator.

Start in Minutes, Not Weeks

Launch a Ready-Made Template and Customize It Your Way

Every template is fully editable. Adjust fields, workflows, and branding to match your processes, then deploy to your team instantly.