Site Acceptance Test Record

The recurring failure at SAT is treating it as a formality because the equipment already passed its Factory Acceptance Test. A short trial substitutes for a full shift, a punch list from the FAT reappears unclosed, and the warranty clock starts before the sanitation schedule, training and spares are actually in place. What looked resolved at the supplier's works fails once your product, services and shift pattern are the real test.

KnowMaintainRecordMNT-06955 fields across 7 sectionsFull researchSee the form

Reviewed by Siddarth SinghCSPLast reviewed 16 August 2026

Basis
ISO 55001 cl.8.3
Workspace
KnowMaintain
Form type
Record
Completed by
Witnessed by engineering, maintenance and production together
Starts the clock
Warranty and the maintenance plan both begin at acceptance

The short version

  • A Site Acceptance Test only proves what a Factory Acceptance Test could not: how the equipment behaves on your services, your product and your site's shift pattern.
  • Accepted Into Service starts the warranty period and the maintenance plan together — accepting early to hit a go-live date starts both clocks on an asset that isn't actually ready.
  • A sustained run of a full shift catches faults that an hour of running never will; scoring Sustained Run Achieved honestly is what separates a real trial from a demonstration.
  • Training, spares and a loaded PM plan are handover conditions, not paperwork — an asset accepted without them becomes the maintenance team's problem on day one.

What this is

What is a Site Acceptance Test Record?

What is a Site Acceptance Test Record?

A Site Acceptance Test Record is the evidence that equipment performs correctly once installed at your site, with your services connected and your product running through it. It is completed before the equipment is handed over to production, and it is what starts the warranty clock and the maintenance plan. Unlike a FAT, it tests the installation as well as the machine.

Does a passed FAT mean the SAT is just a formality?

No. A Factory Acceptance Test proves the machine as built, on the supplier's services and often on water or a simulant. A Site Acceptance Test proves the same machine as installed, on your services, your product and your shift pattern. Installation deviations, service mismatches and product behaviour differences only show up at SAT, which is why it carries its own acceptance criteria rather than repeating the FAT's.

What does accepting a Site Acceptance Test actually start?

Acceptance starts two things at once: the supplier's warranty period, recorded against Warranty Start Date, and the asset's ongoing maintenance plan, confirmed by PM Plan Loaded. Accepting with an unresolved punch list or an unloaded PM plan starts both clocks on an asset that isn't actually ready to be maintained.

Scope

When is a site acceptance test record required?

This record proves the equipment as installed and running on your site. Using it to repeat the factory test, or to record the physical installation build, blurs work that belongs to the templates either side of it.

Use this template when

  • Equipment with a closed, or explicitly tracked, FAT punch list has been installed and connected to site services
  • A new record is needed; each one gets its own ID in the form SAT-2026-000
  • You are running the Capital Projects and Commissioning programme and this is the pre-handover step
  • The Pre-Commissioning Checklist (MNT-067) has confirmed the installation is safe to energise and run
  • A linked record needs this one to exist: links Asset, Vendor

Do not use it for

  • Pre-Commissioning Checklist, which confirms a new installation is complete and safe before it is energised or run, ahead of any SAT testing.
  • Factory Acceptance Test Record, which records testing of new equipment at the supplier's site before it ships, not after it is installed.
  • Project Handover Record, which records the formal handover of the whole project to operations, not the acceptance test of one asset.
  • Installation Progress Record, which tracks the physical build on site, not the performance test that follows it.
  • Anything outside KnowMaintain, which belongs in the workspace that owns that process

Compliance mapping

Which ISO 55001 cl.8.3 requirements does this satisfy?

ISO 55001 cl.8.3 expects assets to be verified against acceptance criteria before being relied upon in service. For a SAT that verification has to happen with the asset actually installed and running.

ClauseRequirementWhere it lands
ISO 55001 cl.8.3The asset, its FAT record and its pre-commissioning checklist are cross-referenced before site testing beginsHeader
ISO 55001 cl.8.3Installation is verified against supplier requirements and services are confirmed before performance testing startsInstallation verification
ISO 55001 cl.8.3Each test is checked against a stated acceptance criterion and a pass or fail recorded, witnessed by productionTests
ISO 55001 cl.8.3Output, quality and duration are proven with real product under real operating conditions, not a short demonstrationProduction trial
ISO 55001 cl.8.3Cleaning and, where relevant, allergen removal are validated on site rather than assumed from the FATCleaning and hygiene validation
ISO 55001 cl.8.3Training, spares, documentation and the maintenance plan are confirmed in place before handoverHandover readiness
ISO 55001 cl.8.3A scored outcome and an explicit in-service decision close the record and set the warranty start dateOutcome

What it does not cover

  • Sustained Run Achieved, which recorded under an hour of running for equipment later found unstable over a full shift.
  • FAT Punch List Closed, which was marked Partly with no record of what remained open or who owned it.
  • Cleaning Validated By Swabbing, which was answered No with no ATP Swab ID attached to explain why.
  • PM Plan Loaded, which was answered No while Accepted Into Service was marked Yes.
  • Operator Training Delivered, which was answered Partly with no plan recorded for closing the gap before go-live.

Global

Site Acceptance Test Record requirements by country

A Site Acceptance Test sits at the point where machinery safety regimes, food hygiene rules and warranty terms all meet on your own premises.

European Union

Regulation (EC) 852/2004 on the hygiene of foodstuffs

Requires food business operators to ensure equipment and installations are suitable for their purpose and can be adequately cleaned, applied at the point the equipment enters use.

Cleaning Validated By Swabbing and Allergen Removal Validated are where that suitability is actually demonstrated on site, rather than assumed from the equipment's design.

United Kingdom

Regulation (EC) 852/2004 as retained in UK law, enforced via the Food Safety and Hygiene (England) Regulations 2013 and equivalents

Carries the same equipment hygiene and cleanability requirements into UK law post-Brexit, enforced by local authority food safety officers.

A SAT that skips swab validation leaves the site with no on-site evidence to show an inspector that new equipment actually meets the hygiene requirement, not just the supplier's design claim.

United States

FDA Food Safety Modernization Act preventive controls, 21 CFR Part 117

Requires food facilities to control hazards, including those introduced by new equipment, as part of their food safety plan.

Rated Output Achieved On Site and the cleaning validation fields are the evidence a preventive controls plan would expect before new equipment is treated as validated for production use.

How to complete it

How to complete a site acceptance test record, step by step

A record with every field answered Yes is not the same as a record that will hold up once the asset is running production week after week. These are the calls that decide whether it does.

Whether the trial actually ran long enough to mean anything

Sustained Run Achieved is the field most likely to be scored generously under go-live pressure. A full shift catches thermal drift, product build-up and fatigue failures that a demonstration run never will — treat anything short of that as an incomplete trial, not a passed one.

Whether an open FAT punch list was actually closed, or just carried forward

FAT Punch List Closed scoring 'Partly' should stop the SAT, not just get noted. An item deferred at FAT and never revisited at SAT is an item nobody currently owns.

Whether cleaning validation is evidence or assumption

Cleaning Procedure Trialled proves the procedure can be followed; Cleaning Validated By Swabbing proves it actually removes what it's supposed to remove. Accepting the first as a substitute for the second is common and wrong — they answer different questions.

Whether accepting 'with punch list' actually starts the warranty clock fairly

Accepted Into Service allows a conditional pass, but Warranty Start Date should reflect what was actually delivered, not the calendar date convenient for the project plan. A warranty clock started on an asset with known open items burns warranty time against faults that were already known.

What auditors find

Most common site acceptance test record findings

Patterns that show up across SAT records once you compare enough of them.

FindingClauseWhat fixes it
Sustained Run Achieved is scored 'Full shift' on a run that was actually a few hoursISO 55001 cl.8.3Require the actual run duration to be logged against Trial Batch Reference or Result before Sustained Run Achieved can be marked Full shift.
FAT Punch List Closed is marked Yes with no reference back to the actual punch list itemsISO 55001 cl.8.3Make the FAT Record ID link mandatory before FAT Punch List Closed can be scored, so the claim can be checked against the source record.
Cleaning Validated By Swabbing is answered Yes with no ATP Swab ID on fileISO 55001 cl.8.3Require ATP Swab ID whenever Cleaning Validated By Swabbing is Yes; treat a Yes with no reference as unverified.
Accepted Into Service is marked Yes while PM Plan Loaded or Spares On Site are still NoISO 55001 cl.8.3Gate Accepted Into Service on Handover readiness fields scoring Yes, or Partly with a closure date, not on the production trial alone.
Warranty Start Date is set to the planned go-live date rather than the date the record was actually acceptedISO 55001 cl.8.3Populate Warranty Start Date from the signature date, not from the project schedule.
Quality Meets Specification is scored against a visual check rather than the linked quality inspectionISO 55001 cl.8.3Require a Quality Inspection ID reference before Quality Meets Specification can be scored Yes for anything with a quality hold point.

Case in point

Case in point: the SAT that started a warranty clock on a machine that wasn't clean

A filling line's Site Acceptance Test recorded Cleaning Procedure Trialled as Yes and Cleaning Validated By Swabbing as Yes, with no ATP Swab ID attached to either. Accepted Into Service was marked Yes, Warranty Start Date was set to the go-live date, and the line was handed to production the same day.

Three days later a routine swab from the quality team came back over limit on the same equipment, triggering a hold on finished product and a retrospective cleaning validation that should have happened before acceptance, not after. The warranty clock was already running, so the cost of the extra validation and the held stock fell on the site, not the supplier.

The template

The template, field by field

The form exactly as it installs. Every field, option, score and conditional rule is editable, and the links to other templates come with it.

55fields
7 sections
Reference
MNT-069
Archetype
Record
Record ID
SAT-2026-000
Scoring
Pass or fail
Direction
High is good
Singleton
No
Basis
ISO 55001 cl.8.3
Links
Links Asset, Vendor
Tags
Commissioning, Lifecycle
Sections
7
Fields
55
Follow up fields
3
Repeating sections
1
Links out
8
Field typesOwn ID, generated on saveCase thread and parentPick list from a registryLinked to another templateFollow up, dashed outlineScored

Header

13 fields
Text

Record ID*

Generated on save

Auto sequence. Format SAT-2026-000.

The record's own ID. Other templates point at this value.

Single Choice

Status*

Scored

Drives who this goes to next.

  • Planned2 pts
  • In progress2 pts
  • Complete3 pts
  • Deferred0 pts
  • Open0 pts
  • Closed3 pts
  • Overdue0 pts
Date & Time

Date and Time*

Users

Raised By*

Pick List

Site*

From FDN-001 Site NameFilter: Status is Active
Text

Site ID*

Linked

Format SITE-000.

Links to FDN-001 Site ID

Single Choice

Area

Optional

The area within the site.

Cutting roomBoning hallPackingChill storeFreezerPasteurisingFillingCulture roomDespatchYardWorkshopPlant roomOffices
Location

Exact Location

Optional

Drop a pin for anything hard to find.

Pick List

Asset*

From FDN-002 Asset NameFilter: Site matches, Status is Active
Text

Asset ID*

Linked

Format AST-0000.

Links to FDN-002 Asset ID

Text

FAT Record ID

OptionalLinked

Links to MNT-068 Record ID

Text

Pre-Commissioning Checklist ID

OptionalLinked

Links to MNT-067 Checklist ID

Single Choice

Supplier Present*

Scored
  • Yes3 pts
  • No1 pt

Installation verification

3 fields
Single Choice

FAT Punch List Closed*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Installed Per Supplier Requirements*

Scored
  • Yes3 pts
  • Minor deviation1 pt
  • No0 pts
Single Choice

Services Verified*

Scored
  • Yes3 pts
  • No0 pts

Tests

Repeats6 fields
Text

Test Description*

Text

Acceptance Criteria*

Text

Result*

Single Choice

Passed*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Witnessed By Production*

Scored
  • Yes3 pts
  • No0 pts
File Upload

Evidence

Optional

Production trial

6 fields
Single Choice

Trial Run With Real Product*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Rated Output Achieved On Site*

Scored
  • Yes3 pts
  • Marginal1 pt
  • No0 pts
Single Choice

Quality Meets Specification*

Scored
  • Yes3 pts
  • Marginal1 pt
  • No0 pts
Numeric Answer

Trial Batch Reference

OptionalLinked

Links to External system reference

Text

Quality Inspection ID

OptionalLinked

Links to QUA-014 Inspection ID

Single Choice

Sustained Run Achieved*

Scored

Running for an hour proves less than running a full shift. Ask for the shift.

  • Full shift4 pts
  • Several hours2 pts
  • Under an hour0 pts

Cleaning and hygiene validation

5 fields
Single Choice

Cleaning Procedure Trialled*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Cleaning Validated By Swabbing*

Scored
  • Yes3 pts
  • No0 pts
Text

ATP Swab ID

OptionalLinked

Links to QUA-033 ATP ID

Single Choice

Allergen Removal Validated

OptionalScored
  • Yes3 pts
  • Not applicable3 pts
  • No0 pts
Single Choice

Sanitation Schedule Updated*

Scored
  • Yes3 pts
  • No0 pts

Handover readiness

6 fields
Single Choice

Operator Training Delivered*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Maintainer Training Delivered*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

PM Plan Loaded*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Spares On Site*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Single Choice

Documentation Complete*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Text

Commissioning Record ID

OptionalLinked

Links to MNT-042 Record ID

Outcome

16 fields
Numeric Answer

Items Assessed*

Excludes anything marked N/A.

Numeric Answer

Items Failed*

Numeric Answer

Score Percent*

Scored

Calculated on submission. High is good. N/A items leave the denominator.

Single Choice

Result Band*

Scored
  • Pass3 pts
  • Caution1 pt
  • Fail0 pts
Numeric Answer

Completeness Percent*

How much of the template was actually answered. A high score on a half completed form is not a high score.

Numeric Answer

Punch List Items Remaining*

Scored
Single Choice

Accepted Into Service*

Scored
  • Yes3 pts
  • With punch list1 pt
  • No0 pts
Date & Time

Warranty Start Date

Optional
Single Choice

Action Required*

Scored

Raise the action record, then enter its reference here.

  • No2 pts
  • Yes0 pts
Single Choice

Priority

OptionalScoredShows if Action Required equals Yes
  • High0 pts
  • Medium1 pt
  • Low3 pts
Text

CAPA ID

OptionalLinkedShows if Action Required equals Yes

Format CAPA-2026-00000.

Links to FDN-014 CAPA ID

Users

Action Owner

OptionalShows if Action Required equals Yes
Users

Engineering*

Signature

Signature*

Users

Production Manager*

Signature

Second Signature*

MNT-069 · record IDs look like SAT-2026-000 · Links Asset, Vendor

Open in Knowella

Run it with agents

From a document you fill in to a programme that runs itself

The form is the easy part. Confirming the trial ran long enough, the cleaning was actually validated, and handover conditions were met before the warranty clock starts is the work that actually slips.

KnowMaintain

Holds the Site Acceptance Test Record against the asset, cross-references it to the FAT and pre-commissioning checklist, and loads the PM plan the moment the asset is accepted.

KnowQuality

Tracks the cleaning and swabbing evidence behind a SAT and flags an accepted asset with no ATP Swab ID reference on file.

KnowTrain

Confirms operator and maintainer training records actually match what Handover readiness claims was delivered, before the asset goes live.

Ella
Ella

Chases outstanding sign-offs and punch list items across every open SAT, and holds every write for your approval before it touches a record.

This template lives in KnowMaintain — asset maintenance. Work orders, planned maintenance, calibration, reliability and shutdowns.

Meet KnowMaintain→

Glossary

Site Acceptance Test Record definitions and key terms

SAT
Site Acceptance Test. Testing carried out after installation at your site, proving the machine as installed and running your product.
Sustained run
A production trial held for long enough, ideally a full shift, to expose faults that only appear under continuous operation.
ATP swabbing
A cleaning validation method that measures residual organic matter on a surface as a proxy for how thoroughly it was cleaned.
PM plan
The preventive maintenance plan for an asset, covering scheduled tasks and intervals, that should be loaded before the asset enters service.
Warranty start date
The date from which the supplier's warranty period is measured, which should reflect actual acceptance rather than a planned go-live date.

FAQ

Frequently asked questions about site acceptance test record

What is the Site Acceptance Test Record template based on?+

It is built against ISO 55001 cl.8.3, which covers verifying assets against acceptance criteria before they are relied upon. ISO 55001 is the international standard for getting value from physical assets across their whole life, and it underpins the maintenance templates in this library.

What sections does the Site Acceptance Test Record contain?+

There are seven sections: Header, Installation verification, Tests, Production trial, Cleaning and hygiene validation, Handover readiness, and Outcome. Together they hold 55 fields, 41 of which are required.

How often is a Site Acceptance Test Record raised?+

A new record is raised once equipment is installed and connected to site services and ready to test before handover to production. Each one is given an ID in the form SAT-2026-000, cross-referenced back to its FAT Record ID and Pre-Commissioning Checklist ID.

Which programme does the Site Acceptance Test Record belong to?+

It is part of Capital Projects and Commissioning, the programme that carries equipment from specification through to a post-project review, so it arrives with its procedures, training and spares rather than after them.

How is a Site Acceptance Test Record scored?+

Scoring is pass or fail, with high scores good throughout. Fields like Sustained Run Achieved and Cleaning Validated By Swabbing carry more weight than a bare Yes or No, because they distinguish a trial that proves something from one that only looks complete.

Can the Site Acceptance Test Record template be changed?+

Yes. Every field, option, score and conditional rule is editable, and the links to the Asset, Vendor, FAT and Pre-Commissioning Checklist records come with it. Most teams install it as it is, run it through one project, then adjust the handover readiness fields to match their own training and spares process.

Keep going

Related templates and programmes

Siddarth Singh

Written and reviewed by

Siddarth Singh

Founder & Chief Executive Officer, Knowella

Certified Safety Professional and industrial and systems engineer with more than a decade inside food supply chain, freight and manufacturing operations. This page was written against the current text of the standards it cites, not against secondary summaries of them.

  • Certified Safety Professional (CSP), Board of Certified Safety Professionals
  • MBA, University of Chicago Booth School of Business
  • MS and BS, The Ohio State University, Industrial and Systems Engineering
  • Six Sigma Black Belt
Verify with BCSP →

Sources and last review. Reviewed 16 August 2026 against:

  • ISO 55001:2014 cl.8.3 — Asset management systems, Operation
  • Regulation (EC) 852/2004 — Hygiene of foodstuffs
  • 21 CFR Part 117 — FDA preventive controls for human food
  • Food Safety and Hygiene (England) Regulations 2013

This page is general guidance, not legal advice. Confirm requirements with your jurisdiction’s regulator.