Knowella

Insurance Adequacy Review

An insurance adequacy review checks whether the limits and types of cover a contractor holds actually match the risk of the work they are doing, which is a different question from whether they hold cover at all. Its recurring failure is running the check once at prequalification against a generic risk profile, then never rerunning it when the scope of work changes to something the original limits were never sized for.

KnowContractorReviewCON-022Pinned in navigation43 fields across 4 sectionsFull researchSee the form

Reviewed by Siddarth SinghCSPLast reviewed 16 August 2026

Basis
Contract requirements
Workspace
KnowContractor
Form type
Review
Completed by
Carried out by procurement with risk management
Raised
At the review interval, and after any trigger event

The short version

  • Adequacy is set by the exposure of the work, not by the size of the contractor or a standard contract clause. A one-size limit applied to every contractor produces cover that is wrong for most of them.
  • Required and held have to be compared as numbers, not inferred from a yes on a certificate. An adequacy field marked yes while the held figure is below the required figure is a review that has not actually been done.
  • A shortfall found today does not retroactively fix itself at the next renewal. Whether work continues meanwhile, unconditionally, with conditions, or not at all, is a decision this review has to make explicitly.
  • Design or specification work by a contractor creates a professional liability exposure that public liability does not cover, and treating professional indemnity as optional whenever design is involved is a common and specific gap.
  • Scope change is the trigger most often missed. A review run at prequalification against one scope of work says nothing about adequacy once that scope changes to something with a materially different worst case.

What this is

What is an insurance adequacy review?

What is an insurance adequacy review?

An insurance adequacy review compares the insurance a contractor holds, by type and limit, against the actual exposure of the work they are contracted to do. It asks whether the cover matches the risk, which is distinct from confirming the cover simply exists or has not expired.

How is adequacy different from a certificate check?

A certificate check confirms a policy is current and lists its stated limits. Adequacy asks whether those limits are enough for what could plausibly go wrong on this specific scope of work, which requires assessing the exposure first and only then judging the cover against it.

Why does this need risk management involvement, not just procurement?

Procurement can confirm a certificate matches a contract clause. Judging whether a limit is actually adequate for a given exposure, a fire, a product recall, an environmental release, requires the kind of loss-scenario thinking risk management does, which is why the review is carried out jointly rather than by procurement alone.

Scope

When is an insurance adequacy review required?

This review sits downstream of a risk classification and upstream of the contract terms it is meant to enforce. Using it to confirm a certificate exists, rather than to judge whether the cover fits the risk, collapses it into a check it was not built to be.

Use this template when

  • A contractor is being prequalified and the required cover for their risk tier needs setting and checking
  • The scope of a contractor's work has changed materially since the last review, in method, hazard or location
  • A contract is being renewed or extended and the original limits need reconfirming against current exposure
  • An incident or near miss involving a contractor raises a question about whether the cover in place was ever adequate
  • A risk tier has been reassigned and the required limits attached to it need to be reapplied

Do not use it for

  • Insurance Certificate Record, which holds the contractor's insurance certificates with coverage amounts and expiry dates as documents, not as an adequacy judgement
  • Workers Compensation Clearance, which confirms a statutory account is current and paid, not whether commercial limits fit the risk
  • Insurance Expiry Review, which tracks contractor insurance due to expire across the approved list on a calendar basis
  • Contractor Risk Classification, which sets the risk tier this review depends on, rather than judging any single contractor's cover
  • Indemnity and Contract Record, which holds the contractual indemnity allocation rather than the insurance limits that stand behind it

Compliance mapping

Which Contract requirements requirements does this satisfy?

Insurance adequacy is driven overwhelmingly by contract, not statute: what the parties agreed to require sits above any general legal minimum, which is why the review's authority is the contract itself, with statutory minimums acting as a floor rather than the standard.

ClauseRequirementWhere it lands
ISO 45001:2018 cl.8.1.4.2Coordinate with contractors to identify hazards and control risks arising from contracted work before it proceedsHeader
Employers' Liability (Compulsory Insurance) Act 1969 (UK)Employer must hold a minimum statutory level of employers' liability cover for its own workforceRequired versus held
ISO 45001:2018 cl.8.1.4.2Risk arising from contracted activities is assessed and controlled in proportion to the activity itselfExposure assessment
State-mandated minimum liability limits (US, no federal minimum)Minimum general or public liability cover is set by the jurisdiction in which the work is performedRequired versus held
Contract requirements (bespoke to the engagement)The coverage type and limit specified in the contract must be evidenced against the risk before work proceeds, not assumed from a certificateAssessment
ISO 45001:2018 cl.8.1.4.3Outsourced functions and processes are controlled so risk is not transferred to a party without matching capability or coverAssessment
Common law and statutory indemnity principlesA principal that knowingly accepts inadequate contractor cover retains exposure for losses the contractor cannot payExposure assessment

What it does not cover

  • Insurance Certificate Record, which holds the contractor's insurance certificates with coverage amounts and expiry dates as documents on file.
  • Workers Compensation Clearance, which confirms a statutory account is current and paid, a separate question from whether commercial limits fit the risk.
  • Insurance Expiry Review, which tracks contractor insurance due to expire across the approved list, on a calendar basis rather than an adequacy basis.
  • Contractor Risk Classification, which sets the risk tier this review consumes, rather than judging any individual contractor's cover.
  • Indemnity and Contract Record, which holds the contractual indemnity allocation between the parties, distinct from the insurance limits standing behind it.

Global

Insurance Adequacy Review requirements by country

Because adequacy is contract-driven, statutory minimums function mainly as a floor beneath the negotiated requirement, and the jurisdictions that matter most are the ones with clear statutory minimums or a litigation environment that pushes contract limits well above them.

United Kingdom

Employers' Liability (Compulsory Insurance) Act 1969

Sets a clear statutory minimum for employers' liability cover, giving reviewers a hard floor to check contractor cover against for their own workforce.

Public and product liability limits above that floor remain a matter of contract, so the review still has to judge adequacy for anything beyond the statutory minimum.

United States

State-mandated minimum liability limits, no federal general scheme

Minimums vary by state and by line of cover, and a litigious claims environment means contract-required limits routinely run far above any statutory floor.

The statutory minimum is rarely the relevant number; the contract-required limit, set from the actual exposure, is what a review here should be checking.

International

ISO 45001 cl.8.1.4 and national contract insurance practice

ISO 45001 requires risk from contracted work to be controlled proportionate to the activity, without prescribing insurance limits, leaving the specific figures to contract and national practice.

Outside the UK and US, adequacy is judged almost entirely against the contract and the exposure assessment, since a comparable statutory floor is often absent or unclear.

How to complete it

How to complete an insurance adequacy review, step by step

The form pairs a required figure with a held figure for each type of cover, which makes the arithmetic easy. The judgement is in what required figure gets entered in the first place, and what happens once a gap is found.

Size the exposure before sizing the limit

The required limit should come out of the worst credible outcome fields, injury severity, property damage, business interruption, recall, environmental damage, assessed for this scope of work, not out of a standard contract clause applied regardless of the work. A required figure with no exposure reasoning behind it is a guess with a number attached.

Compare required against held as numbers, not impressions

Adequacy is a numeric comparison, and marking it without checking the two figures against each other defeats the purpose of recording them separately. Where the held figure is unclear from the certificate, that is itself a finding, not a reason to mark the field on faith.

Treat design work as a professional indemnity trigger

Public liability does not respond to a claim arising from a design or specification error; that sits with professional indemnity. Any contractor whose scope includes design, engineering judgement or specification should have professional indemnity assessed as required, not left at the default of not needed.

Decide what happens to the work meanwhile

A shortfall does not resolve itself by being recorded. Whether work stops, continues under specific conditions, or continues unconditionally while cover is corrected is a decision this review has to state, and it should default toward caution rather than toward keeping the contractor working.

What auditors find

Most common insurance adequacy review findings

Because adequacy depends on a judgement about the exposure, findings against this review are less about missing numbers and more about numbers that were never actually tested against each other.

FindingClauseWhat fixes it
Required limit set to a standard contract figure rather than derived from the exposure assessed for this scope.Contract requirements (bespoke to the engagement)Derive the required limit from the worst credible outcome fields for this specific work, not a boilerplate contract number.
Adequate marked yes while the held figure is numerically below the required figure.Contract requirements (bespoke to the engagement)Cross-check the required and held figures before marking adequacy; do not infer adequacy from the certificate existing.
Professional indemnity marked not required despite the contractor performing design or specification work.ISO 45001:2018 cl.8.1.4.2Flag professional indemnity as required whenever the scope includes design, specification or engineering judgement.
Work permitted to continue unconditionally despite an identified shortfall.Common law and statutory indemnity principlesDefault to holding or conditioning the work whenever a shortfall is identified, until it is corrected or contractually addressed.
Contract requirements not updated after a shortfall is found, leaving the same gap at the next renewal.Contract requirements (bespoke to the engagement)Link a confirmed shortfall to a contract amendment step, rather than leaving it as a note on this record alone.
Risk tier and required limits not reassessed after a scope change.ISO 45001:2018 cl.8.1.4.3Trigger the exposure assessment and required limits again whenever the scope of work changes materially.

Case in point

Case in point: the certificate that matched the wrong risk

A cleaning contractor was prequalified for routine floor and surface cleaning, and the insurance adequacy review set required public liability at a moderate figure suited to that scope. Several months in, the contract was extended to include periodic drain and pipework treatment near an ammonia refrigeration plant, a change agreed directly between the site manager and the contractor without a new adequacy review.

A treatment chemical reacted with residue in the drain line, causing an environmental release that required regulatory notification and remediation costing several times the contractor's public liability limit. The review on file was accurate for the scope it had assessed and irrelevant to the scope actually being performed, because nothing had linked the contract change to a rerun of the exposure assessment. The lesson taken forward was procedural rather than technical: any scope change now routes automatically to a new adequacy review before the changed work is permitted to start.

The template

The template, field by field

The form exactly as it installs. Every field, option, score and conditional rule is editable, and the links to other templates come with it.

43fields
4 sections
Reference
CON-022
Archetype
Review
Record ID
IAR-2026-000
Scoring
Adequacy score
Direction
High is good
Singleton
No
Basis
Contract requirements
Links
Links Vendor, Risk Classification
Tags
Contractor, Insurance
Sections
4
Fields
43
Follow up fields
3
Repeating sections
0
Links out
3
Field typesOwn ID, generated on saveCase thread and parentPick list from a registryLinked to another templateFollow up, dashed outlineScored

Header

12 fields
Text

Review ID*

Generated on save

Auto sequence. Format IAR-2026-000.

The record's own ID. Other templates point at this value.

Single Choice

Status*

Scored

Drives who this goes to next.

  • Planned2 pts
  • In progress2 pts
  • Complete3 pts
  • Deferred0 pts
  • Open0 pts
  • Closed3 pts
  • Overdue0 pts
Date & Time

Date and Time*

Users

Completed By*

Pick List

Site*

From FDN-001 Site NameFilter: Status is Active
Text

Site ID*

Linked

Format SITE-000.

Links to FDN-001 Site ID

Pick List

Contractor*

From FDN-005 Vendor NameFilter: Status is Approved
Text

Vendor ID*

Linked

Format VEN-0000.

Links to FDN-005 Vendor ID

Single Choice

Work Category*

Mechanical, electrical, refrigeration, civil, cleaning, catering, transport, IT or professional services.

MechanicalElectricalRefrigerationCivilCleaningCateringTransportITProfessional servicesPest control
Single Choice

Risk Tier*

Scored

Set by the work they do, not by how big the company is.

  • Low3 pts
  • Medium2 pts
  • High1 pt
  • Very high0 pts
Users

Contract Owner*

Info

Match The Limit To The Exposure

A million in cover sounds like a lot until a contractor causes a fire or a product recall. Set required limits by what could actually go wrong, not by habit.

Exposure assessment

6 fields
Single Choice

Worst Credible Injury Outcome*

Scored
  • Minor3 pts
  • Serious1 pt
  • Fatality0 pts
Numeric Answer

Worst Credible Property Damage

OptionalScored
Numeric Answer

Business Interruption Exposure

OptionalScored
Single Choice

Product Recall Exposure*

Scored

A contractor contaminating product creates recall, disposal and customer claim costs simultaneously.

  • None3 pts
  • Limited1 pt
  • Significant0 pts
Single Choice

Environmental Damage Exposure*

Scored
  • None3 pts
  • Limited1 pt
  • Significant0 pts
Single Choice

Ammonia Or Major Hazard Exposure*

Scored
  • None3 pts
  • Limited1 pt
  • Significant0 pts

Required versus held

11 fields
Numeric Answer

Public Liability Required*

Numeric Answer

Public Liability Held*

Single Choice

Adequate*

Scored
  • Yes3 pts
  • Marginal1 pt
  • No0 pts
Numeric Answer

Employers Liability Required

Optional
Numeric Answer

Employers Liability Held

Optional
Single Choice

Statutory Minimum Met*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Professional Indemnity Required

OptionalScored

Design work by a contractor creates a professional liability that public liability does not cover.

  • No3 pts
  • Yes1 pt
Numeric Answer

Professional Indemnity Held

Optional
Single Choice

Product Liability Required

OptionalScored
  • No3 pts
  • Yes1 pt
Single Choice

Motor Insurance Where Vehicles On Site

OptionalScored
  • Yes3 pts
  • Not applicable3 pts
  • No0 pts
Single Choice

Contract Works Where Applicable

OptionalScored
  • Yes3 pts
  • Not applicable3 pts
  • No0 pts

Assessment

14 fields
Single Choice

All Required Cover In Place*

Scored
  • Yes3 pts
  • Partly1 pt
  • No0 pts
Text

Shortfall Identified

Optional
Single Choice

Additional Cover Required*

Scored
  • No3 pts
  • Yes0 pts
Single Choice

Contract Requirements Updated*

Scored
  • Yes3 pts
  • Not needed3 pts
  • No0 pts
Single Choice

Contractor Informed*

Scored
  • Yes3 pts
  • No0 pts
Single Choice

Work Permitted Meanwhile*

Scored
  • No3 pts
  • With conditions1 pt
  • Yes0 pts
Single Choice

Action Required*

Scored

Raise the action record, then enter its reference here.

  • No2 pts
  • Yes0 pts
Single Choice

Priority

OptionalScoredShows if Action Required equals Yes
  • High0 pts
  • Medium1 pt
  • Low3 pts
Text

CAPA ID

OptionalLinkedShows if Action Required equals Yes

Format CAPA-2026-00000.

Links to FDN-014 CAPA ID

Users

Action Owner

OptionalShows if Action Required equals Yes
Users

Contract Owner*

Signature

Signature*

Users

Risk Or Finance*

Signature

Second Signature*

CON-022 · record IDs look like IAR-2026-000 · Links Vendor, Risk Classification

Open in Knowella

Run it with agents

From a document you fill in to a programme that runs itself

The review itself is a comparison of numbers. What actually fails is the link between a changed scope and a rerun assessment, and between a found shortfall and a corrected contract.

KnowContractor

Holds the adequacy review against the vendor's risk tier and scope, and flags where a scope change has not triggered a fresh review.

KnowComply

Rolls adequacy findings into the wider contractor compliance picture, so a shortfall is visible alongside expiry and clearance status, not isolated on this record.

Ella
Ella

Watches for scope changes and shortfall findings across the contractor list, and raises the rerun review before work under the new scope proceeds.

This template lives in KnowContractor — contractor management. Prequalification, approval, induction, permits and performance.

Meet KnowContractor→

Glossary

Insurance Adequacy Review definitions and key terms

Adequacy
Whether the type and limit of cover a contractor holds is sufficient for the specific exposure of the work they are doing, as distinct from whether cover simply exists.
Exposure assessment
A structured estimate of the worst credible outcomes, injury, property damage, business interruption, recall, environmental, arising from a given scope of work, used to set required limits.
Statutory minimum
The lowest level of cover required by law in a given jurisdiction, which functions as a floor rather than a target for contract-required limits.
Professional indemnity
Cover responding to loss caused by an error in design, advice or specification, which sits outside what public or general liability cover will pay.
Contract works cover
Insurance covering physical loss or damage to work under construction or installation, relevant wherever a contractor's activity itself could damage the asset being worked on.

FAQ

Frequently asked questions about insurance adequacy review

Isn't a valid certificate enough to prove adequacy?+

No. A certificate proves a policy exists at a stated limit. Adequacy asks whether that limit is enough for this specific work's worst credible outcome, which the certificate alone cannot answer without the exposure assessment behind it.

How do we set the required limit for a new contractor?+

From the exposure assessment, not from habit. Estimate the worst credible injury, property damage, business interruption, recall and environmental outcomes for the actual scope, and size the required limit against those, rather than applying the same figure to every contractor regardless of risk.

When does professional indemnity apply to a contractor?+

Whenever their scope includes design, specification or engineering judgement, not only where they are formally titled a designer. Public liability responds to physical injury or damage; it does not respond to a claim that the design itself was wrong, and that gap is exactly what professional indemnity is for.

What should happen if we find a shortfall?+

Decide explicitly whether work continues meanwhile, stops, or continues under stated conditions, and update the contract requirement so the shortfall does not simply recur at the next renewal. Recording the shortfall without a decision is not a completed review.

Does a scope change really require a whole new review?+

Yes, wherever the change is material to the exposure. Limits set for one description of work say nothing about a materially different one, and the review's value depends entirely on the exposure it was tested against still matching the work being done.

Who decides what counts as adequate, procurement or risk management?+

Both, deliberately. Procurement can confirm a certificate matches a contract clause, but judging whether a limit is genuinely sufficient for a loss scenario is a risk management judgement, and the review is weakest when either function does it alone.

Keep going

Related templates and programmes

Siddarth Singh

Written and reviewed by

Siddarth Singh

Founder & Chief Executive Officer, Knowella

Certified Safety Professional and industrial and systems engineer with more than a decade inside food supply chain, freight and manufacturing operations. This page was written against the current text of the standards it cites, not against secondary summaries of them.

  • Certified Safety Professional (CSP), Board of Certified Safety Professionals
  • MBA, University of Chicago Booth School of Business
  • MS and BS, The Ohio State University, Industrial and Systems Engineering
  • Six Sigma Black Belt
Verify with BCSP →

Sources and last review. Reviewed 16 August 2026 against:

  • ISO 45001:2018 clause 8.1.4, Procurement
  • Employers' Liability (Compulsory Insurance) Act 1969 (UK)
  • State-mandated minimum liability limits (US, no federal minimum)
  • Contract requirements as the primary basis for required cover

This page is general guidance, not legal advice. Confirm requirements with your jurisdiction’s regulator.

Start in Minutes, Not Weeks

Launch a Ready-Made Template and Customize It Your Way

Every template is fully editable. Adjust fields, workflows, and branding to match your processes, then deploy to your team instantly.