What this is
What is an out of tolerance impact review?
What is an out of tolerance impact review?
A review carried out whenever a gauge, meter or piece of test equipment is found out of calibration, working out what product may have been measured, released or used for a critical control point while the equipment was reading wrong. It sets the look-back window from the last known good calibration, not from the moment the fault was discovered.
Why does the direction of the error matter?
A gauge reading high may have caused good product to be wrongly rejected, a cost problem. A gauge reading low may have let product outside tolerance be accepted and released, a safety and legality problem. The review is built to keep the two separate rather than average them into one severity.
What does Product Still On Site actually decide?
Whether a hold is even physically possible. Product still on site can be quarantined immediately; product already despatched needs recall consideration instead, a more consequential decision the form routes to a separate field.
Scope
When is an out of tolerance impact review required?
This review is one step in a larger programme. Using it for work that belongs to a neighbouring template produces records that are hard to report on later.
Use this template when
- A calibration or verification check has failed and product measured against that equipment needs tracing
- A new record is needed; each one gets its own ID in the form OOT-2026-000
- You are running the Calibration and Measurement programme and this is one of its steps
- A linked record needs this one to exist: links calibration; feeds hold
- Equipment used for product release or a critical control point has returned an out of tolerance result
Do not use it for
- Test Equipment Register, which lists every gauge, meter and instrument and its calibration status, but does not trace what a specific failure affected.
- Calibration Record, which records the calibration event itself, standard used, result and next due date, not what happened downstream of a failure.
- Gage R&R Study, which measures how much of normal measurement variation comes from the gauge and the operator, a different question from a single confirmed failure.
- Calibration Schedule Review, which asks whether the calibration interval itself is set correctly, not what a specific out of tolerance event affected.
- Anything outside KnowQuality, which belongs in the workspace that owns that process
Compliance mapping
Which ISO 9001 cl.7.1.5 requirements does this satisfy?
ISO 9001 cl.7.1.5 does not tell you how to run this review; it tells you that you must. It requires determining whether previously reported measurement results were adversely affected once equipment is found unfit, and taking appropriate action, without prescribing a look-back method, which is left to be defined and followed consistently.
| Clause | Requirement | Where it lands |
|---|---|---|
| ISO 9001:2015 cl.7.1.5.1 | Monitoring and measuring resources must be suitable for their purpose and maintained to ensure continuing fitness | Header |
| ISO 9001:2015 cl.7.1.5.2 | When equipment is found unfit, determine whether previous measurement results were adversely affected and take appropriate action | The error |
| ISO 22000:2018 cl.8.7 | Evaluate results back to the last satisfactory calibration or verification and take action on both the equipment and any product affected | What was measured |
| ISO 9001:2015 cl.8.7 | Identify, control and prevent unintended use or delivery of nonconforming output pending disposition | What was measured |
| ISO 9001:2015 cl.8.6 | Release of product not to proceed until conformity has been verified, unless approved by a relevant authority | Assessment |
| ISO 9001:2015 cl.10.2 | React to nonconformity, evaluate the need for action to eliminate the cause, and implement any action needed | Outcome |
| ISO 9001:2015 cl.8.5.6 | Review and control changes to production or service provision, including changes to monitoring frequency | Outcome |
What it does not cover
- Calibration Record, which documents the calibration event itself, not what it affected downstream.
- Hold Record, which is the actual quarantine instrument; this review decides whether one is needed and links to it, it does not function as one.
- Corrective and Preventive Action, which fixes the cause of the calibration failure; this review decides an action is needed, not what that action contains.
- Gage R&R Study, which measures normal measurement system variation across many readings, not a single confirmed failure.
- Product recall notification, which is a separate regulatory process triggered once recall consideration confirms product has left the site.
Global
Out of Tolerance Impact Review requirements by country
The duty to assess the effect of a calibration failure comes almost entirely from the quality and food safety management standards a site is certified to, rather than from a single national regulation naming test equipment.
FDA Food Safety Modernization Act, Preventive Controls Rule (21 CFR Part 117)
No calibration-tolerance figure is set in regulation; a confirmed control failure feeds the food safety plan's reanalysis and corrective action requirements.
Where the equipment monitors a preventive control, this review has to feed the food safety plan's own corrective action process, not stay inside quality's log.
Regulation (EC) 178/2002 general food law due diligence duty, applied through GFSI-benchmarked scheme audits such as BRCGS or SQF
No statutory tolerance figure; certification schemes require documented handling of measuring equipment found out of calibration as part of due diligence.
An auditor asks for the trace from last known good to the fault, and a review covering only the fault day is a due diligence gap, scheme finding aside.
ISO 9001:2015 cl.7.1.5 and ISO 22000:2018 cl.8.7
Both require determining the effect on previous results when equipment is found unfit, ISO 22000 explicitly extending that to the last satisfactory calibration.
Certification auditors examine whether the look-back window was defined and followed, not just whether the gauge was eventually fixed.
How to complete it
How to complete an out of tolerance impact review, step by step
The fields ask for a date, a direction and a batch count. What determines whether the review is defensible is how far those answers are actually chased down.
Period Affected Days should be calculated from Last Known Good Date forward, not backward from when the fault happened to be noticed. A gauge can drift for weeks before a check catches it, and the review has to own that full window even when it makes the batch list much longer than expected.
Reading low, which may have let out of tolerance product through, deserves a faster response than reading high, which may only have caused over-rejection. Treating both directions as equally urgent slows down the case that actually needs speed.
Product Still On Site, Product Already Despatched and Recall Consideration Required are the substance of the review; Decision and the signatures are the record of that substance, not a substitute. A review reaching Outcome without a clear position on where the product physically is has skipped its own purpose.
Used For A CCP being Yes should raise, not lower, the bar for conformity confirmed. Probable is reasonable for a routine dimensional check; it is not reasonable for a measurement that stood between the process and a food safety hazard, where Cannot Confirm is the honest default absent an actual retest.
What auditors find
Most common out of tolerance impact review findings
Findings on this review cluster around the gap between what was checked, usually the equipment, and what should have been checked, usually the product measured with it.
| Finding | Clause | What fixes it |
|---|---|---|
| Look-back period measured from the date the fault was found rather than the last known good calibration date. | ISO 9001:2015 cl.7.1.5.2 | Calculate Period Affected Days from Last Known Good Date forward; the fault date is irrelevant to the window. |
| A reading-low error, which may have released bad product, handled with the same timeline as a reading-high error. | ISO 9001:2015 cl.7.1.5.2 | Route reading-low findings to expedited review; product may already be with customers. |
| Product Conformity Confirmed marked Probable on a CCP-linked measurement with no product retest performed. | ISO 22000:2018 cl.8.7 | Require Retesting Possible to be Yes, with results recorded, before conformity on a CCP measurement can be anything but Cannot Confirm. |
| Batches Affected recorded only as a count, with no batch numbers, so a hold cannot be raised against anything specific. | ISO 9001:2015 cl.8.7 | Require batch-level identification before Product Affected By The Deviation is answered. |
| Product Already Despatched marked Yes with Recall Consideration Required left blank. | ISO 9001:2015 cl.8.7 | Make recall consideration mandatory whenever despatch has occurred, not conditional on someone remembering to raise it. |
| Calibration Interval Shortened and Verification Frequency Increased both marked Not Required on a review that confirmed the gauge exceeded tolerance, with no rationale recorded. | ISO 9001:2015 cl.8.5.6 | Require a stated reason whenever a confirmed out of tolerance result leaves the monitoring frequency unchanged. |
Case in point
Case in point: the retest that checked the gauge and not the packs
A filling line checkweigher, used as the monitoring instrument for a minimum fill weight critical control point, failed its weekly verification, reading light by more than tolerance. Quality opened the review the same day, marked direction as reading low, and pulled the production log for the day of the failure. The gauge was recalibrated, checked again, and passed. Retesting Possible was marked Yes on the strength of that recheck, and Product Conformity Confirmed was recorded as Probable. No batches were held.
The verification interval was weekly, so the gauge could have been drifting for up to nine days before the failure was caught, not one. A customer complaint about underweight cartons weeks later traced back to production before the day the log had covered, and the nine-day trace showed most of that run already despatched. The retest had confirmed the equipment was now correct; it had never asked whether the nine days of packs it had cleared were correct, the actual question the review existed to answer.
The template
The template, field by field
The form exactly as it installs. Every field, option, score and conditional rule is editable, and the links to other templates come with it.
5 sections
- Reference
- QUA-068
- Archetype
- Review
- Record ID
- OOT-2026-000
- Scoring
- Not scored
- Direction
- n/a
- Singleton
- No
- Basis
- ISO 9001 cl.7.1.5
- Links
- Links Calibration; feeds Hold
- Tags
- Test equipment, Quality
- Sections
- 5
- Fields
- 43
- Follow up fields
- 8
- Repeating sections
- 0
- Links out
- 6
Header
10 fieldsReview ID*
Auto sequence. Format OOT-2026-0000.
The record's own ID. Other templates point at this value.
Status*
Drives who this goes to next.
- Planned2 pts
- In progress2 pts
- Complete3 pts
- Deferred0 pts
- Open0 pts
- Closed3 pts
- Overdue0 pts
Date and Time*
Raised By*
Site*
Site ID*
Format SITE-000.
Links to FDN-001 Site ID
Equipment ID*
Links to QUA-064 Equipment ID
Calibration ID
Links to QUA-065 Calibration ID
Verification Check ID
Links to QUA-067 Check ID
How Far Back Do You Look
The equipment was last known good at its previous calibration. Everything measured since then was measured with an instrument you now know was wrong. Work out what that means before deciding it does not matter.
The error
5 fieldsError Found*
Direction Of Error*
Reading high means product may have been wrongly rejected. Reading low means bad product may have been accepted.
- Reading high, may have over rejected1 pt
- Reading low, may have accepted bad product0 pts
Magnitude Versus Tolerance*
- Within half tolerance2 pts
- Within tolerance1 pt
- Exceeds tolerance0 pts
Last Known Good Date*
Period Affected Days*
What was measured
11 fieldsUsed For Product Release*
Used For A CCP*
Number Of Batches Affected*
Batches Affected*
List them. This is the working list for any hold or recall decision.
Product Still On Site*
- Yes3 pts
- Partly1 pt
- No0 pts
Product Affected By The Deviation*
- No3 pts
- Yes0 pts
Quantity Affected
Hold ID
Raise the hold record, then enter its reference.
Links to QUA-003 Hold ID
Product Location
Where the affected product physically is right now.
Product Already Despatched*
- No3 pts
- Yes0 pts
Recall Consideration Required
- No3 pts
- Yes0 pts
Assessment
6 fieldsRetesting Possible*
- Yes3 pts
- Partly1 pt
- No0 pts
Retest Results
Product Conformity Confirmed*
- Yes3 pts
- Probable1 pt
- Cannot confirm0 pts
Rationale*
Food Safety Impact*
- None3 pts
- Manageable1 pt
- Significant0 pts
Legality Impact*
- None4 pts
- Low3 pts
- Medium1 pt
- High0 pts
Outcome
11 fieldsDecision*
Calibration Interval Shortened*
- Yes3 pts
- Not required3 pts
- No0 pts
Verification Frequency Increased*
- Yes3 pts
- Not required3 pts
- No0 pts
Action Required*
Raise the action record, then enter its reference here.
- No2 pts
- Yes0 pts
Priority
- High0 pts
- Medium1 pt
- Low3 pts
CAPA ID
Format CAPA-2026-00000.
Links to FDN-014 CAPA ID
Action Owner
Quality Manager*
Signature*
Site Manager*
Second Signature*
QUA-068 · record IDs look like OOT-2026-000 · Links Calibration; feeds Hold
Open in KnowellaRun it with agents
From a document you fill in to a programme that runs itself
The review asks the right questions about the equipment. What fails is tracing the product with the same rigour, particularly when the retest checks the gauge and stops there.
Holds the review against the test equipment register and calibration history, so the look-back window is calculated from the actual last known good date.
Links the review to the calibration work orders for the equipment, so a shortened interval or increased frequency decision reaches the maintenance schedule.
Tracks where affected batches physically are, on site, in transit or despatched, so the disposition decision matches reality rather than the production log alone.

Flags CCP-linked measurements where conformity is marked Probable with no recorded product retest, and holds the review open until answered.
This template lives in KnowQuality — quality and food safety. HACCP, nonconformance, traceability, laboratory and customer complaints.
Meet KnowQuality→Glossary
Out of Tolerance Impact Review definitions and key terms
- Out of tolerance
- A calibration or verification result outside the acceptable range for the equipment, confirming it was not measuring accurately at the point it was checked.
- Last known good date
- The date of the previous calibration or verification the equipment passed, which sets the start of the look-back window for what may have been affected.
- Critical control point (CCP)
- A step where control is essential to prevent or eliminate a food safety hazard; a measurement used at a CCP carries a higher standard of proof when the measuring equipment fails.
- Retesting
- Confirming the product itself, not just the equipment, still meets specification. A recalibrated gauge passing its own check is not a retest of the product measured before the recalibration.
- Hold
- A quarantine placed on product still physically on site to prevent its release or use while its status is being determined, tracked in its own record and referenced from this review.
FAQ
Frequently asked questions about out of tolerance impact review
How far back do you look when a gauge fails?+
From the last known good calibration, not the date the fault was discovered. A gauge can be wrong for the entire period since it was last confirmed correct, and the review has to cover that full window even when it is longer than expected.
Does a reading-high error need the same response as reading-low?+
No. Reading high risks wrongly rejecting good product, a cost problem. Reading low risks accepting product outside tolerance, a safety and legality problem. The second deserves faster handling, not the same pace just because they share a form.
Does every out of tolerance finding need a hold?+
Only if product affected is still on site. Product already despatched cannot be held; it needs recall consideration instead, a different and more consequential decision the form keeps separate from the hold field.
How is this different from the calibration record itself?+
The calibration record documents the event: standard used, result, next due date. This review starts where that record ends, asking what was measured while the equipment was wrong, a product and traceability question rather than an equipment one.
When does recall consideration actually get triggered?+
Whenever Product Already Despatched is Yes. It should not depend on someone separately judging the deviation serious enough; despatch of potentially affected product is itself the trigger.
Does leaving the calibration interval unchanged need justification?+
Yes, once a failure is confirmed. Not Required is legitimate for a gauge borderline within an otherwise well-controlled programme, but it needs a stated reason once a failure is confirmed, not a default carried over from before.
Keep going
Related templates and programmes
Industries this is written for
Programmes this belongs to
Used together in Calibration and Measurement
Maintenance Calibration Record
Records calibration of maintenance instruments such as torque wrenches, pressure gauges and multimeters
Instrument Loop Check
Verifies a control instrument reads correctly from sensor through to display or control system
Safety Device Test Record
Tests safety devices such as relief valves, trips and interlocks to prove they operate at their set point
Calibration Schedule Review
Reviews whether calibration intervals are still appropriate based on drift history
Test Equipment Register
Lists every gauge, meter and instrument used to make quality decisions, with its calibration status
Calibration Record
Records the calibration of a piece of test equipment, including standard used, result and next due date
More in Test Equipment
Test Equipment Register
Lists every gauge, meter and instrument used to make quality decisions, with its calibration status
Calibration Record
Records the calibration of a piece of test equipment, including standard used, result and next due date
Gage R&R Study
Measures how much of the observed variation comes from the measurement system rather than the product, separating repeatability of the gauge from reproducibility between operators
Equipment Verification Check
A quick daily or weekly check that an instrument still reads correctly against a known standard

Written and reviewed by
Siddarth Singh
Founder & Chief Executive Officer, Knowella
Certified Safety Professional and industrial and systems engineer with more than a decade inside food supply chain, freight and manufacturing operations. This page was written against the current text of the standards it cites, not against secondary summaries of them.
- Certified Safety Professional (CSP), Board of Certified Safety Professionals
- MBA, University of Chicago Booth School of Business
- MS and BS, The Ohio State University, Industrial and Systems Engineering
- Six Sigma Black Belt
Sources and last review. Reviewed 16 August 2026 against:
- ISO 9001:2015 clause 7.1.5, monitoring and measuring resources
- ISO 22000:2018 clause 8.7, control of monitoring and measuring
- ISO 9001:2015 clause 8.7, control of nonconforming outputs
- ISO 9001:2015 clause 10.2, nonconformity and corrective action
This page is general guidance, not legal advice. Confirm requirements with your jurisdiction’s regulator.